Chapter Two: Installation
Setup
13
Setup
Follow the guidelines listed below when setting up an 1100 Series MFC:
1. Place the 1100 Series MFC where it will be connected to a gas supply and process
chamber.
2. Mount the MFC into position.
Mounting of flow components in other than the position in which they are calibrated
(typically horizontal) will cause a small zero shift. The zero offset can be removed
according to the instructions in Warm Up and Start Up, page 25.
3. Install the MFC in the gas stream such that the flow will be in the direction of the arrow
on the side of the controller's base.
4. Be sure to allow clearance for the cable connector and tubing:
Straight Shielded connectors require approximately 3” (76.2 mm) height.
Right Angle connectors require approximately 2” (50.8 mm) height.
5. Be sure to allow access to the zero potentiometer.
Refer to Figure 6, page 18, for the location of the zero potentiometer.
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com