Post Construction Installation
!
!
IMPORTANT! - MAKE SURE WALL ELECTRICITY IS
TURNED OFF BEFORE STARTING INSTALLATION
1. Mark wall with template, using a stud finder
to maintain a 2" distance from any stud. Make
sure that you are clear of any crossbraces in
the wall structure.
4. Tape speaker wire to the back wall so the
end is within the opening as shown.
5. Place the first section of the foam strip and
insert the corner through the wall opening.
6. Continue to insert the remaining foam
strips into the wall opening until the foam
frame is created. (See pg. 5)
2. Cut opening precisely with drywall
saw, drywall router, etc. Sand edges
and clean debris from installation area.
3. BE-65 Model includes 4 foam pieces
to be placed in the wall space around
the speaker.
Be careful when bending and handling
the foam so that you do not rip it.
8. Mount the adhesive backed foam
pad in the wall behind the woofer.
(4)
speaker
wire
Note: Do not put any other acoustic
filler within the wall opening as it can
interfere with speaker mounting.
7. Make sure that the frame is centered
within the opening.
FOR STANDARD INSTALLATION
DRYWALL THICKNESS CANNOT
EXCEED 1.25 INCHES.
FOR THICKER WALLS CALL
M&K SOUND.
If you are installing your new speaker into existing walls, please see the section on post
construction installation below.
If you are installing your speakers into walls that are new construction, use the Pre-Construction
Bracket Instructions that are included with your Pre-Construction Bracket Kit SPRE95; also see
page 7.
DETERMINE INSTALLATION METHOD
For best performance, the BE-65
should be located as close to the floor and
corner of the room as possible. In most
situations, the cut-out should be 4
1/4
" above the floor.