81
-
Number
01
02
03
04
05
07
11
21
22
23
24
27
28
29
31
32
34
35
36
37
(Operation mode)
(Indoor unit heat exchanger temperature 1)
(Indoor unit heat exchanger temperature 2)
(Indoor unit fan speed)
(Indoor unit operation hours)
(Outside air temperature)
(Outdoor unit heat exchanger temperature 1)
(Outdoor unit heat exchanger temperature 2)
(Discharge pipe temperature)
(Outdoor unit fan speed)
(Compressor operation hours)
(Expansion valve opening 1)
SET TEMP
RETURN AIR
I/U HEAT EXCH 1
I/U HEAT EXCH 2
I/U FAN
TOTAL I/U RAN
OUTDOOR
O/U HEAT EXCH 1
O/U HEAT EXCH 2
COMP HERTZ
DISCHARGE
DOME BOTTOM
CT
O/U FAN
SILENT MODE ON/OFF
63H1 ON/OFF
DEFROST ON/OFF
TOTAL COMP RUN
EEV 1
Data item
SW5-3
ON
OFF
Function
Cooling during a test run
Heating during a test run
Normal or After the test operation
SW5-4
OFF
ON
-
(9)
Test run
(a) Test run from an outdoor unit.
1)
Test run method
a)
A test run can be initiated from an outdoor unit by using SW5-3 and SW5-4 for on-site setting.
b) Switching SW5-3 to ON will start the compressor.
c)
The unit will start a cooling operation, when SW5-4 is OFF, or a heating operation, when SW5-4 is ON.
d) Do not fail to switch SW5-3 to OFF when a test run is completed.
1)
Cooling test operation procedure
Carry out the following test operation procedure using the remote controller.
a) Starting the cooling test operation
1
Press the ON/OFF button to start operation.
2
Press the MODE button and select “
(COOL)”.
3
Press the TEST button continuously for 3 seconds or longer.
The display changes from “
SELECT ITEM”
“
SET"
“
TEST RUN
”.
4
When “
TEST RUN
” is displayed, press the SET button to begin the cooling test operation.
The display shows “
TEST RUN.”
b) Canceling the cooling test operation
Pressing the ON/OFF button or the TEMP
button ends the cooling test operation.
The “
TEST RUN” display is cleared.
(b) Test run from remote controller.