7-4 GAS CHARGE

1

Connect gas cylinder to the service port of stop valve (3-way).

2

Execute air purge of the pipe (or hose) coming from refrigerant gas cylinder.

3

Replenish specified amount of the refrigerant, while operating the air conditioner
for cooling.

Note:

In case of adding refrigerant, comply with the quantity specified for the refrigerating
cycle.

 CAUTION

Do not discharge the refrigerant into the atmosphere.

Take care not to discharge refrigerant into the atmosphere during installation,
reinstallation, or repairs to the refrigerant circuit.

When charging the refrigerant system with additional refrigerant, be sure
to use liquid refrigerant.

Adding gas refrigerant may change the composition of the refrigerant in the
system and affect normal operation of the air conditioner. Also, charge the
system slowly, otherwise the compressor will be locked.

To maintain the high pressure of the gas cylinder, warm the gas cylinder with warm
water (under 40°C) during cold season. But never use naked fire or steam.

1

Remove the screw caps.

2

Remove three screws.

3

Pull the bottom.

Hold this concave section and pull the bottom
forward to remove the front panel.

4

Release the hooks.

Push

Go down

Square hole

5

Push

Horizontal vane

3

2 4

1

Point the
horizontal
vane slightly
downward.

7. FOR MOVEMENT AND MAINTENANCE

7-1 REMOVING AND REINSTALLING THE FRONT PANEL

FRONT PANEL REMOVAL

FRONT PANEL REINSTALLATION

Note:

Do not open the front panel up beyond the level position.
The panel may come off in order to prevent it from being damaged.

1

Set the horizontal vane to the position as below before reinstalling the front
panel.

2

Attach the bottom of the front panel under the horizontal vane.

3

Fit in the top of the front panel.

4

Fit in the bottom of the front panel and tighten it using screws.

5

Push the section of the front panel marked by the arrow and fit the panel into the
air conditioner.

7-2 PUMPING DOWN

When relocating or disposing of the air conditioner, pump down the system following
the  procedure below so that no refrigerant is released into the atmosphere.

1

Connect the gauge manifold valve to the service port of the stop valve on the gas
pipe side of the outdoor unit.

2

Fully close the stop valve on the liquid pipe side of the outdoor unit.

3

Close the stop valve on the gas pipe side of the outdoor unit almost completely
so that it can be easily closed fully when the pressure gauge shows —0.101 MPa
[Gauge] (0 kgf/cm

2

).

4

Start the EMERGENCY COOLING OPERATION.
To start the EMERGENCY OPERATION in COOL MODE, disconnect the power
supply plug and/or turn off the breaker. After 15 seconds, connect the power
supply plug and/or turn on the breaker, and then press the EMERGENCY
OPERATION switch once. (The EMERGENCY COOLING OPERATION can be
performed continuously for up to 30 minutes.)

5

Fully close the stop valve on the gas pipe side of the outdoor unit when the
pressure gauge shows 0.05 to 0 MPa [Gauge] (approx. 0.5 to 0 kgf/cm

2

).

6

Stop the EMERGENCY COOLING OPERATION.
Press the EMERGENCY OPERATION switch twice to stop the operation.

7-3 REMOVING THE INDOOR UNIT

Remove the bottom of the indoor unit from the installation plate.

1

Remove the front panel. (See FRONT PANEL REMOVAL shown above.)

2

Insert flat screwdrivers into the square holes at the left and right bottom of the
indoor unit and push them up; the bottom of the indoor unit goes down and the
hooks are released.

Union

Indoor unit

Liquid pipe

Gas pipe

Stop valve

Service port

Gauge manifold valve
(for R410A)

Charge hose (for R410A)

Outdoor unit

Refrigerant gas
cylinder operating
valve

Refrigerant gas cylinder for
R410A with siphon

Refrigerant (liquid)

Electronic scale for
refrigerant charging

Содержание MSZ-GA50VA

Страница 1: ...r or wall and set the wireless remote controller In rooms where inverter type fluorescent lamps are used the signal from the wireless remote controller may not be received 1 THE FOLLOWING SHOULD ALWAYS BE OBSERVED FOR SAFETY Be sure to read THE FOLLOWING SHOULD ALWAYS BE OBSERVED FOR SAFETY before installing the air conditioner Be sure to observe the cautions specified here as they include importa...

Страница 2: ...D CONNECTIONS This unit has flared connections on both indoor and outdoor sides Remove the outdoor units valve cover then connect the pipe Refrigerant pipes are used to connect the indoor and outdoor units Be careful not to crush or bend the pipe in pipe bending Limits MSZ GA50 60 71 80 Pipe length 30 m max Height difference 15 m max No of bends 10 max Refrigerant adjustment If pipe length exceeds...

Страница 3: ... 3 CONNECTING WIRE SPECIFICATIONS Use special room air conditioning circuit 4 4 INDOOR AND OUTDOOR CONNECTING WIRE CON NECTION You can connect indoor outdoor lead wire without removing the front panel 1 Open the front panel 2 Remove one screw holding the electrical cover then remove the cover 3 Remove the VA clamp and the cord clamp 4 Pass the indoor outdoor unit connecting wire from the back of t...

Страница 4: ... is off To prevent breaker off due to the rush of starting current systematize other home appliances not to turn on at the same time 4 6 PIPE FORMING Place the drain hose below the refrigerant piping Make sure that the drain hose is not heaved or snaked Do not pull the hose to apply the tape When the drain hose passes the room be sure to wrap insulation material obtain able at a store around it Wr...

Страница 5: ...ow Connect the refrigerant piping with the extension pipe Thrust the lower part of the indoor unit into the installation plate 4 7 DRAIN PIPING If the extension drain hose has to pass through a room be sure to wrap it with commercially sold insulation The drain hose should point downward for easy drain flow Fig 1 Do not make drain piping as shown in Fig 2 to 5 Spacer assembly Securely attach the s...

Страница 6: ... substituted for R410A tools The diameter of the service port on the stop valve in outdoor unit has been changed to prevent any other refrigerant being charged into the unit Cap size has been changed from 7 16 UNF with 20 threads to 1 2 UNF with 20 threads R410A tools Can R22 tools be used Description R410A has high pressures beyond the meas urement range of existing gauges Gauge manifold No Port ...

Страница 7: ...perates so the compressor will not operate for three minutes to protect the air conditioner 6 6 EXPLANATION TO THE CUSTOMER Using the OPERATING INSTRUCTIONS explain the following to the customer how to control temperature how to remove the air filters how to remove or put the remote controller in the remote controller holder how to clean precautions for operation etc Recommend the customer to read...

Страница 8: ...e top of the front panel 4 Fit in the bottom of the front panel and tighten it using screws 5 Push the section of the front panel marked by the arrow and fit the panel into the air conditioner 7 2 PUMPING DOWN When relocating or disposing of the air conditioner pump down the system following the procedure below so that no refrigerant is released into the atmosphere 1 Connect the gauge manifold val...

Отзывы: