Test run [for wireless remote controller]
Measure an impedance between the power supply terminal block on
the outdoor unit and ground with a 500V Megger and check that it is
equal to or greater than 1.0M
"
.
1
Turn on the main power to the unit.
2
Press the button twice continuously.
(Start this operation from the status of remote controller display
turned off.)
A
and current operation mode are displayed.
3
Press the ( ) button to activate mode, then
check whether cool air is blown out from the unit.
4
Press the ( ) button to activate mode, then
check whether warm air is blown out from the unit.
5
Press the button and check whether strong air is blown out
from the unit.
6
Press the button and check whether the auto vane operates
properly.
7
Press the ON/OFF button to stop the test run.
Note:
• Point the remote controller towards the indoor unit receiver
while following steps
2
2
to
7
7
.
• It is not possible to run the in FAN, DRY or AUTO mode.
MODE
MODE
COOL
HEAT
TEST RUN
FAN
VANE
TEST RUN
(2) Outdoor Unit
1) Check Items
• After installation of indoor and outdoor units, and tubing and electric wiring work, check that the unit is free from leaks of refrigerant, loosened
connections, and incorrect polarity.
• Check that there is no negative phase and open phase. (The F1 message for negative phase and the F2 message for open phase will flash
at digital indicator LED 1 on the outdoor substrate. If this happens, rewire correctly.)
• Measure the impedance between power terminals (Single phase: L,N,
;
;
/ triple phase: L1,L2,L3,
;
;
) and the ground with a 500V Merger and
check that it is 1.0M
Ω
or more. Do not operate the equipment if measurement is less than 1.0m
Ω
. *Never conduct this operation on the out-
door connection wiring terminals (S1,S2,S3) as this causes damage.
• When there is no error at the outdoor unit.
(If there is an error at the outdoor unit, it can be evaluated at LED 1 [digital display] of the outdoor substrate.)
• The stop valves are open both the liquid and gas sides.
After checking the above, execute the test run in accordance with the following.
2) Test run start and finish
• Operation from the indoor unit
Execute the test run using the installation manual for the indoor unit.
• Operation from the outdoor unit.
Execute settings for test run start, finish and operation mode (cooling, heating) using the DIP switch SW 4 on the outdoor substrate.
1
Set the operation mode (cooling, heating) using SW4-2.
2
Turn ON SW 4-1, The operation mode for SW 4-2 will be adhered to, and the test run will commence.
3
Turn OFF SW 4-1 to finish the test run.
• There may be a faint knocking noise emitted from the proximity of the fan during the test run. This is torque
fluctuation occurring due to control of fan revolutions. There is no problem with the product.
Note:
The SW 4-2 operation mode cannot be changed during the test run. (To change run mode, stop the equipment with SW 4-1, change
the operation mode, then restart test run with SW 4-1.)
ON
SW4
1 2
A
Stop
B
Cooling
C
Operation
D
Heating
A
C D
B
(Factory setting)