Initial operation
© MIG·O·MAT GmbH
BA_Lötstar_EN_Vers. 07.2016
25
Follow the instructions given in
Section
8.1.1. Check and refill
demineralized water in the reactor
. When the glass floating body in
the filling duct (see
illustration 8.1.1
.
A
.) goes down by more than
1 cm, refill demineralized water.
Switch the unit back into operating mode at the
on/on
key
I/O
in the operating panel.
Acknowledge the filling level check with key
(
Yes
) in the
operating panel.
6.4
Leak check
The programme offers to carry out a leak check. You are asked
to decide if you wish to have an automatic leak check carried
out. We recommend to carry out the leak check on a daily
basis.
The leak check can only be carried out with cold electrolyte
reactor (below 45°C).
Check for leaks?
No
Yes
Confirm the request with the key
(Yes) at the operating
panel.
You are now asked to check and confirm that the valve at the
burner hand piece and the filling ducts at the reactor and the
vaporizer glass are shut.
Close the burner valve!
Confirm with the key
(
OK
) at the operating panel.
The Lötstar unit now starts carrying out an automatic leak
check. Please wait until the display indicates the result of the
leak check. This takes approx. 25 to 30 seconds!
If there is a leak, the display shows:
Unit is leaking!
Repair the leak!
The leak must be found and repaired before the unit is
operated.
Check if the screw connections between gas hose and reactor
outlet and between gas hose and outlet at the top part are
correctly tightened; also check the screw connections at the
burner hand piece and at the filling ducts for electrolyte and
vaporizer liquid. When in doubt contact your supplier or the
manufacturer of the unit.
Leak check
Shut the valve at the
burner hand piece
and shut the reactor
closing caps
If the unit is leaky