  Turn on boiler at isolator and on/off on boiler control panel 

– the burner should start 

its start-up and ignition process.

 

  Check gas train (gas burner) and any pipework between isolating valve and burner 

connection for leakage.

 

  Check oil lines / oil connections for soundness (oil burner).

 

 

Adjust burner in accordance with the burner manufacturer’s instructions and allow the 
burner to stabilise for approximately 10 

– 15 minutes; following which take 

measurements of combustion gases, fuel throughput (gas burner) and making any 
further adjustments as necessary.  Record measurements.

 

  Switch off boiler, remove any gauges and refit test points.

 

  Restart/stop boiler several times to check integrity of ignition system.

 

  Check combustion chamber door for correct sealing.

 

  Check flue joints for integrity.

 

  Check water connections for soundness.

 

  (For gas fired burner only), with burner firing, turn off gas supply and ensure burner 

goes to lockout. Wait 45 seconds, turn on gas supply, and press reset button on 
burner 

– ensure burner restarts normally.

 

  Set controls to normal operational settings.

 

  Instruct user on the operation of the boiler and its controls and safety functions.

 

User Instructions 

  Following  the  successful  installation  and  commissioning  procedures,  the  user  must 

be  made  aware  of  the  lighting  and  operating  instructions  including  a  practical 
demonstration.

 

  This installation guide plus the burner instructions must handed over for safe keeping 

and future reference.

 

Operation / Controls 

  The control panel includes two control thermostats which allows for the operation of 

high / low firing (2 stage burners). 

  The left hand thermostat is for the control of the first stage (low fire) and should be 

set  to  the  actual  final  wanted  flow  temperature;  the  right  hand  thermostat  is  for  the 
control  of  the  second  stage  (high  fire0  and  should  be  nominally  set  around  3-5 
deg

rees lower than the first stage thermostat to allow the burner to reduce to it’s low 

fire setting as the final setpoint water temperature is approached.  

Содержание SupeRAC - 2F 105

Страница 1: ...ler Models 93 to 405 Installation Operating and Service Manual MHS Boilers Ltd 3 Juniper West Fenton Way Basildon Essex SS15 6SJ Main Tel 01268 546700 Spares Tel 01268 546771 Service Tel 01268 546770...

Страница 2: ...ion page 8 Location page 8 Combustion chamber door opening and adjustment page 8 Burner mounting page 9 Prevention of condensation page 9 Fuel supply page 10 Fitting appliane case panels mount control...

Страница 3: ...or Biodiesel Net Efficiency 90 3 to 91 0 Suitable for low temperature hot water heating systems up to 95 C with working pressures up to 6bar Floor space saving double stacked arrangement with two or f...

Страница 4: ...SupeRAC 2F For Models 93 to 405 4 MHS Boilers 29 05 2013 Technical Data...

Страница 5: ...parts may be used when replacing components on the boiler otherwise warranty will be void Application The SupeRac 2F Boiler may be used for heating and hot water production purposes only The boiler s...

Страница 6: ...s having electrical connections The following Codes of Practice are also applicable BS 6644 2011 Specification for gas fired hot water boilers of rated inputs between 70kW net and 1 8MW net 2nd and 3r...

Страница 7: ...in the form of this book in order to ensure that these target groups have all the information they need As the supplier we would be happy to help you in connection with any additional information tha...

Страница 8: ...iler to allow the removal of the burner and opening of the combustion chamber door see clearances Combustion chamber door opening and adjustment The boiler is supplied with the door opening front left...

Страница 9: ...mportant to ensure that the return water temperature entering the boiler is maintained above the dew point temperature of the flue gases An acceptable method of creating of this facility is to install...

Страница 10: ...ot considered suitable The oil supply pipe should terminate adjacent to the burner with an isolating valve and should include metal bowl type filter Fitting the case and Mount Control Panel See Fig 1...

Страница 11: ...ted The route of the flue short be as short as possible and sized appropriately to ensure complete evacuation of combustion gases without causing excessive back pressure The flue should generate suffi...

Страница 12: ...with a good quality corrosion inhibitor and the water condition must be maintained to ensure that the following values are observed pH 8 3 9 5 Hardness 100mg CaCO3 litre Chlorides 50mg litre Oxygen 0...

Страница 13: ...Models 93 to 405 13 MHS Boilers 29 05 2013 Control panel schematic IG Isolator TSAH Limit thermostat TR1 1st Stage thermostat TR2 2nd Stage thermostat TA External enable contacts remove link if conne...

Страница 14: ...supplies have been appropriately tested for soundness have been purged vented and the fuel control valve is closed Ask to view certificates Gas supplies should be tested and purged in accordance IGE U...

Страница 15: ...urn off gas supply and ensure burner goes to lockout Wait 45 seconds turn on gas supply and press reset button on burner ensure burner restarts normally Set controls to normal operational settings Ins...

Страница 16: ...gas firing or 50 C for oil firing If a modulating burner is being used then the 4 core burner connection lead T6 T8 T7 should be ignored and not utilised The thermostat sensing bulb for the 2nd stage...

Страница 17: ...SupeRAC 2F For Models 93 to 405 17 MHS Boilers 29 05 2013 Notes...

Отзывы: