12
REGENCY2
L O W
P R O F I L E
legend of control panel components
A
Power On Lamp
B
Pump Run Lamp
C
High Limit Lamp
D
Pump Run On Timer (Eberle Type)
E
Boiler Run Lamp
F
Gas Valve Connections
G
External Controls Contacts (volt free) High/Low
H
Reset
I
Lockout Lamp
J
Boiler Pump
K
High Fire Lamp
L
Remote Overheat Trip Indicator Lamp
M
Remote Burner Lockout Indicator Lamp
N
External Clock (motor)
O1 & O2
Gas Valves
P
Control Box
Q
Ignition Probe
R
On/Off Switch
S
Detection Probe
T
Flue Limit Thermostat
T.R.I.
Control Thermostat
T.R.II.
High/Low Thermostat
T.S.
Limit Thermostat
X
Cable + PLUG Connections
Y
External Controls Contacts (volt free) On/Off
Denotes Field Wiring by Installer
Note:
Configuration of BMS relays subject to alteration without notice.
3 way relay boards supplied when all BMS outputs are required.
3.6 electrical supply
& connection
The boiler requires a 230 volts 50Hz Ac electrical supply - fuse rating is 5 amps: preferably by means
of un-switched shuttered socket outlet in conjunction with a fused three pin plug, both complying with the
requirements of BS1363. Alternatively, a fused double pole switch or fused spur box connection to the
mains, should be readily accessible and adjacent to the boiler.
The boiler should be connected using heat resisting cable. The method of cable entry should be from
the rear left hand side of the boiler with the cables being retained in the cable tray/bracket attached to the
side of the panel.
All wiring external to the boiler must be installed in accordance with the latest and current I.E.E. and
Local Authority Regulations.
control panels and electrical connection
There are a number of differing control panels which are supplied with the Regency2 range of boilers.
Please refer to the following list for the correct matching of control fascia for the chosen boiler.
Boiler Model Fully Automatic Versions
G100, 30, 40, 50IE
G100/70IE
G100/90, 110IE
Control Panel Type
CC 147
CC 148
CC 149
Содержание REGENCY 2 G100/110IE
Страница 1: ...G U I D E T O I N S T A L L A T I O N S E R V I C E C L E A N I N G REGENCYL O W P R O F I L E L 111 ...
Страница 17: ...17 REGENCY2 L O W P R O F I L E fig 1 fig 2 fig 3 fig 4 1 9 5 10 2 3 5 4 12 4 8 6 7 3 1 2 ...
Страница 19: ...19 REGENCY2 L O W P R O F I L E 4 1 atmospheric boiler service commissioning report S A M P L E ...
Страница 21: ...21 REGENCY2 L O W P R O F I L E fig 5 fig 6 fig 7 fig 8 17 18 17 18 19 20 21 22 21 23 ...