background image

P 10

Please retain product label and instructions for future reference

             

It is ESSENTIAL that you apply wood treat-

ment immediately after the building has 

been assembled.

15

15

15

15

Step 18

Parts Needed - No. 15 QTY 4

Align the fascia’s (

No. 15

)

with the roof and fix into

place using 3x40mm

screws per fascia, making

sure to screw through the 

fascia into the roof purlins

and eaves frame.

*Ensure the angled cuts meet

at the top of the apex.

12x40mm Screws

Pre drill 

hole

40mm 

screw

Pre drill 

hole

60mm 

bolt

Step 19

Parts needed - No. 19 QTY 8

Arrange the storm braces (

No. 19

)

around the building (

internally

). 

Place 2x storm braces per side 

fixing into place using 2x 60mm 

bolts per brace making sure the 

washer & nut are tightened from 

the outside of the building.

*Ensure the storm braces are

secured at the highest point

possible on each side.

**Storm braces will help your

building expand and contract

properly.

***Important: Ensure each

bolt is tightened using a 

washer so as not to damage 

the log boards.

16x60mm Bolt Sets

IMPORTANT: 

Pre-drill before fixing screws.

19

19

Содержание 0619LOG003-V4

Страница 1: ...ain or snow BUILDING A BASE When thinking about where the building and base are going to be constructed Ensure that there will be access 60cm to all sides for maintenance work and annual treatment Ens...

Страница 2: ...16 C 2760 Roof Board 121x16x1752mm QTY 56 MB16 C 1752 2 1 Short Window Pack QTY 2 Double Door Pack Closure Trim 16x28x2400mm approx length QTY 14 S1628 2400 P 2 0619LOG003 V4 Overall Dimensions Width...

Страница 3: ...assembly Please note Each board interlocks at either end in a staggered pattern Before securing ensure that the boards are fitted properly in their respective tongues and grooves P 3 Please retain pro...

Страница 4: ...ange the remaining framing No 14 inside the assembled frame Ensure there is an equal amount of space between each frame Secure each of the frames in place using 2x70mm screws for each side of the bear...

Страница 5: ...ition Nevertheless the process of fitting the door frame is the same Please Note The short boards at the front of the building either side of the door and window opening s can be placed either side de...

Страница 6: ...of the window and door frames Ensure that the boards are level and flush with each other as you lay each one Doors can be hung once the boarding has enclosed the door frame 9 20 21 24 3 3 Step 9 Part...

Страница 7: ...sembly on each side making sure the boards are flush to the end of the roof purlin Once in position fix to each purlin using 3x40mm screws Due to natural occurences of wood shrinkage expansion You may...

Страница 8: ...QTY 27 Place the first floor board No 17 inside the building flush to the log board on one side Continue adding the floor boards internally making sure to interlock each individual board Following th...

Страница 9: ...per trim equally spacing them along the face of the board 42x30mm Screws 30mm screw Pre drill hole Cut to fit Step 16 Parts needed No 11 QTY 7 Once the floor has been laid arrange the closure trim No...

Страница 10: ...the apex 12x40mm Screws Pre drill hole 40mm screw Pre drill hole 60mm bolt Step 19 Parts needed No 19 QTY 8 Arrange the storm braces No 19 around the building internally Place 2x storm braces per side...