10.12 Sealing ventilation pipes on external wall
NOTICE
If the external plaster encloses the
ventilation pipes all round and without
gaps, you can skip the steps described
in this section.
►
Chamfer both pipe breakthrough
edges (item 1 in Fig. 20) to roughly
5x45° to create enough space for the
sealing joints with permanently elastic
sealant.
►
Fill the chamfers of the pipe break-
through edges all-round with perma-
nently elastic sealant on the outside.
NOTICE
Only use a solvent-free sealant if the sealant is applied to polystyrene.
10.13 Attaching the outer wall terminal
WARNING
Do not run without the outer wall
terminal
Please note that the ventilation unit
must not be used without the outer
wall terminal for safety reasons.
►
Attach the outer wall terminal to the
external wall.
NOTICE
Installation of the outer wall terminal
is described in a separate installation
manual (see “1.11 Supplementary