If necessary, use a screwdriver to punch through the sealed hole (item B in Fig. 12).
►
Thread the control cable, if required (item 4 in Fig. 12) through the hole B (item B in Fig. 12).
►
Push the wall box (item. 5 in Fig. 12) fully into the wall breakthrough.
7.7
Inserting the cardboard insert and protective cover
►
Place the cardboard insert (item 1 in Fig.
13) in the wall box (item 4 in Fig. 13).
►
Insert the protective cover (item 2 in Fig.
13) into the wall box (item 4 in Fig. 13) as
far as it will go.
►
Check that the red signal cover (item 3 in
Fig. 13) is seated in the protective cover.
7.8
Fixing the wall box
►
Fix the wall box (item 1 in Fig. 14) in posi-
tion in the wall breakthrough using wedges
(item 2 in Fig. 14).
►
Use the spirit level (item 3 in Fig. 14) to
align the wall box so that it is perpendicular
and flush with the wall.
NOTE
►
Make sure that the wall box is perpendicu-
lar as this is the only way to ensure that any
condensation will be carried outside by the
2° pipe fall.
►
If you are using the filler piece, fix it in place
on the outer wall using wedges.
Fig. 13: Inserting the cardboard insert and pro-
tective cover
Fig. 14: Fixing the wall box