3 - 3
Operation
Remove Heater
Remove the pipe and the fitting from the heater.
TX01407-6-17-10
PH
04
20
5-6
-11-10
Inspect Melt
Quickly inspect the heated parts to make sure all surfaces have
been melted properly.
If melt is not complete, cut off melted pipe end. Use a new fitting
and repeat preparation and heating process.
TX01408-6-20-97
PH
04
20
7-
6-11-10
Fusion and Cooling
Within 3 seconds after the heater has been removed, firmly push
the melted fitting squarely onto the pipe until it makes firm contact
with the cold ring clamp.
NOTICE:
Do not twist or rotate the fitting.
Hold the fitting firmly in place for the total cooling time specified
by the pipe manufacturer to ensure proper alignment.
TX01409-6-20-97
PH
04
20
8-6
-11-10
Inspecting Fusion Joint
After completing the pipe manufacturer’s specified cooling time,
remove the cold ring clamp and the socket fitting holder.
Inspect the joint. A good joint will have a uniform melt ring that is
flat against the socket fitting and perpendicular to the pipe.
There should be no gaps or voids between the fitting and the
pipe.
TX01410-6-20-97