2.3.
BEF-04,
BEF-05
AND
BEF-075
INSTALLATION
1.
Remove the upper deck from the unit.
2.
Clean the reservoir and remove any dust or contaminant.
3.
Connect the overflow fitting to a proper external reservoir or drain.
4.
Clamp and insulate both glycol lines to the pump outlet and to the unit return fitting. Repeat this step
for each pump.
5.
Fill the reservoir with
propylene glycol
solution (mixed 2 parts water to 1 part glycol).
6.
Place back the upper deck on the unit.
7.
Plug the unit and the pump to an appropriate electrical circuit. This task should be executed by a
professional electrician in compliance with national electrical standards.
8.
Inspect the unit for any leakage.
9.
Glycol temperature should be adjusted to 28°F. Set point should be reached within a few hours.
NOTE: To adjust the glycol temperature, please see section 2.4.
2.4.
A
DJUSTING THE TEMPERATURE CONTROLLER
Instructions for all models