16
Mass Combi Ultra, Mass Combi Pro
– Installation Manual Multiple Units
Three-phase configuration with MasterAdjust
5.5
Network wiring of three-phase units
5.6
Configuration with MasterAdjust
Pre-commissioning
1. Make sure that the units are switched off.
2. Make sure that all connections are firmly tightened.
3. Install the DC fuses and close the battery switch.
4. Close the covers of all units.
5. Switch on all units.
6. If not already available, connect a MasterBus USB Interface to the MasterBus network and to a PC, and open MasterAdjust.
Installation or configuration errors may come up in MasterAdjust while the configuration is in progress. This is normal.
Configuration
7. In MasterAdjust, check that the units are running the latest firmware. See the Mastervolt Portal for more information.
8. In the device list, in the left pane of MasterAdjust, right-click the L1 unit and select
Login
.
9. Select
Installer
and enter the installer code.
10. Go to the Configuration tab and give the unit a logical name. For example, MCU L1, MCU L2 and MCU L3.
11. Return to the Configuration tab of the L1 unit. All settings are done here. However, if Mastervolt Lithium-Ion batteries are
connected, all events, like Stop Discharge for example, must be configured for ALL units separately.
12. In the
Cluster
pane, from the
Phase System
drop-down list, select
Three Phase
. You may need to maximize the
MasterAdjust window or scroll all the way to the right to see this.
L1
L2
L3
Battery
temperature
sensor
Sync cable
MasterBus cable
MasterBus
network or
terminator
Battery temp.
sensor
Battery temp.
sensor
Sync cable
MasterBus cable
MB
network
or term.