6  ASSEMBLY AND DISMANTLING 

6.1  General information

a)  For assembly and dismantling of the mobile access towers, at least 2 people are necessary 

and it is indispensable they are familiar with the assembly and use instructions;

b)  based on the height which must be reached, choose to set up one of the configurations 

outlined on page 7. The list, the weight and quantity of the elements necessary for assembly 

are outlined on page 5.

c)  no damaged components must be used;
d)  only original parts must be used as indicated by the manufacturer.

6.2  Preliminary tests

a)  The surfaces on which the tower is assembled and subsequently moved (if necessary) must 

be capable of supporting the weight, it must be perfectly level and guarantee distribution 

of the load, perhaps using planks or other equivalent devices;

b)  absence must be ensured of obstacles;
c)  the assembly operations can only start in the absence of wind;
d)  all the elements must be checked, accessory tools and safety equipment to assemble the 

tower are available on site;

e)  The verticality of the mobile towers must be checked with the level supplied.

6.3  Assembly instructions

Having conducted the checks on par. 6.2, proceed to assemble the base section:

Check the 2-wheel support blocks with 

the base batten using the 2 handle screws, 

supplied.  

Before completely tightening the screws, 

assemble the first 2 side frames and insert 

the fastening pins in the hole on the base 

sleeve. Tighten the screws, proceed to insert 

the brakes in the 4 wheels and, if using the 

adjustable feet, on horizontal extraction of 

these, the maximum quantity compatible 

with the surrounding dimensions, a specific, 

automatic device prevents its unintentional 

removal, then tighten the extraction fastening 

screw; then, level the base section working on 

the feet screw and having taking care to lift all 

the wheels off the ground at least 20 metres, 

on levelling tighten the specific counter-nuts.

Содержание OLYMPO

Страница 1: ...means working in compliance with the provisions of the current standard on health and safety in the workplace Leg Decree 09 04 2008 no 81 Code 11115 CUSTOMER ASSISTANCE DOCUMENT N 120 REV 2 DATED 08...

Страница 2: ...ow the instructions as indicated Before any installation verify the integrity of each individual component Do not use damaged or not whole components The mobile access tower is made according to the s...

Страница 3: ...TOWER DESIGN pag 8 CONFIGURATIONS UNI EN 1004 pag 9 6 ASSEMBLY AND DISMANTLING pag 10 6 1 General information pag 10 6 2 Preliminary tests pag 10 6 3 Assembly instructions pag 10 6 4 Dismantling instr...

Страница 4: ...G no 235 on 08 10 05 Ordinary Supplement no 162 Consumers Code 2 DESIGNATION CLASS CAPACITY OLYMPO working tower EN 1004 3 5 5 XXCD manufactured in compliance with Leg Decree 81 08 and Technical Stan...

Страница 5: ...prototype which has surpassed rigidity testing pursuant to Appendix A of the Technical Standard EN 1004 2005 and that it was subject with a positive outcome with the ASSESSMENT as outlined in point 1...

Страница 6: ...4 2 Maximum heights of the configuration EN 1004 The maximum height of the work platform without using the stabilizer braces is 1 60 metres maximum tower height 2 90 metres The maximum height of the...

Страница 7: ...1093 Short toeboards 75 0 75 2 2 2 6 11092 Long toeboards 180 3 00 2 2 2 21324 Guardrail 7 33803 Single parapet 2 00 2 2 2 20770 Stabilizer braces 8 20765 Stabilizer brace 35 Normal 9 80 0 4 4 9 31377...

Страница 8: ...8 www marchetti eu OLYMPO TOWER DESIGN BASE TOWER FINAL TOWER GUARDRAIL WORK PLATFORM STABILIZERS BRACES 14 3 2 2 12 11 10 4 13 1 8 9 7 5 6 9...

Страница 9: ...H Tower 2 00 H Working 0 80 A1T H Tower 2 90 H Working 1 60 A2 H Tower 3 70 H Working 2 40 A2T H Tower 4 60 H Working 3 30 A3 H Tower 5 40 H Working 4 10 A3T H Tower 6 20 H Working 5 00 CONFIGURATIONS...

Страница 10: ...embly operations can only start in the absence of wind d all the elements must be checked accessory tools and safety equipment to assemble the tower are available on site e The verticality of the mobi...

Страница 11: ...mentsofthescaffolding on the fourth rung from the bottom of the first two side frames firstly position the 2 long toeboards parallel to the treadable surface then the 2 short toeboards fitting them in...

Страница 12: ...he joint on the riser of the tower at a height to fit the upper vertical part of the brace Repeat the operation with a second joint in the same riser distancing it adequately from the first to fit the...

Страница 13: ...g the necessary operations in the inverse order to those for assembly the elements composing the towers must be lowered from above using ropes or other suitable devices avoiding sudden impact with the...

Страница 14: ...re a the mobile access towers can only be moved manually on compact smooth surfaces free of obstacles perfectly level and in the absence of wind b before moving lift the adjustable feet off the ground...

Страница 15: ...ore use Strictly complying with this manual means operating in accordance with the provisions of existing legislation on health and safety at work Legislative Decree 09 04 2008 no 81 Instructions for...

Страница 16: ...Leg Decree 81 08 but not with UNI EN 1004 they must have the base wheels braked during use and positioned on an already perfectly level floor and have stabiliser feet when present removed to the maxim...

Страница 17: ...ope anchored on top of the last upright of the last side support frame and under the wheel support block of the base section The fall proof device the safety harness and the holding rope must be certi...

Страница 18: ...welding Lubrication of tightening screws Lubrication of pins and sleeves Efficiency of wheels and braking devices Integrity of work platforms Integrity of railings Integrity of toe boards Integrity of...

Отзывы: