CRANE INSTALLATION
800D
10-4
Published 5-27-2018 Control # 039-06
19. Continue winding the cable on the second, third and
fourth layer of the drum. Keep the cable paying in
straight to the boom to avoid side loading the boom. The
preceding layers will wrap smoothly guided by the first
layer wrapping.
20. After cable is completely wrapped on drum, replace
remaining cable keeper bolts on the sheave case.
Attach wedge socket and cable clip to end of cable per
illustration in Loadline Section of parts manual and
torque cable clip bolts to 95 lb-ft (128.8 Nm) for 9/16 inch
cable.
21. Check for hoist mount tail swing clearance at top of cab.
Any equipment that extends above the truck cab such as
exhaust stacks or air horns may interfere with the hoist
mount when the boom is elevated and rotated. Shorten
exhaust stacks or move air horns, etc. to ensure
clearance.
22. If crane is to be repainted, mask all decals prior to final
paint or install all new decals in accordance with location
drawings and illustrated parts catalog over final paint.
23. After installation, check all oil and lubricant levels and
lubricate unit according to “Lubrication Chart” on page 4
in Service and Maintenance Section.
Rope size
3/8
7/16
1/2
9/16
5/8
3/4
7/8
1
1-1/8
1-1/4
*Torque lb-ft (Nm)
45 (61)
65 (88)
65 (88)
95 (128.8)
95 (128.8)
130 (176)
225 (305) 225 (305) 225 (305) 360 (488)
* The tightening torque values shown are based upon the threads being clean, dry, and free of lubrication.
20 × Rope Diameter
11.25 In (292 mm)
Minimum
WRONG
Rope
Backward
WRONG
Wedge
Backward
WRONG
Tail Clipped
to live Line
RIGHT
“Go”
“No-Go”
•
Properly match socket, wedge and clip to wire rope size. The wire rope must pass through the “go”
hole in the wedge. It must not pass through the “no go” hole in the wedge.
•
Align live end of rope, with center line of pin.
•
Secure dead end section of rope.
•
Tighten nuts on clip to recommended torque. (See Table)
•
Do not attach dead end to live end or install wedge backwards.
•
Use a hammer to seat Wedge and Rope as deep into socket as possible before applying first load.
FIGURE L
Terminator Type Wedge Installation
9448
Fo
r
Reference
Only
Содержание National Crane 800D
Страница 1: ...Operator and Service Manual National Crane 800D F o r R e f e r e n c e O n l y ...
Страница 4: ...F o r R e f e r e n c e O n l y ...
Страница 98: ...MAINTENANCE 800D 3 10 Published 5 27 2018 Control 039 06 THIS PAGE BLANK F o r R e f e r e n c e O n l y ...
Страница 194: ...SPECIFICATIONS 800D 8 4 Published 5 27 2018 Control 039 06 THIS PAGE BLANK F o r R e f e r e n c e O n l y ...
Страница 216: ...INSTALLATION 800D 9 22 Published 5 27 2018 Control 039 06 THIS PAGE BLANK F o r R e f e r e n c e O n l y ...
Страница 232: ...CRANE INSTALLATION 800D 10 16 Published 5 27 2018 Control 039 06 THIS PAGE BLANK F o r R e f e r e n c e O n l y ...
Страница 252: ...SCHEMATICS 800D 2 Published 5 27 2018 Control 039 06 F o r R e f e r e n c e O n l y ...
Страница 255: ...F o r R e f e r e n c e O n l y ...
Страница 256: ...F o r R e f e r e n c e O n l y ...