30
Position:
1
SEDM-L
2
Solid / gypsum wall construction
3
British gypsum thistle bond 60
(or equivalent can by used)
minimum density 670 kg/m³)
/
Ablative Coated Batt
(e.g. Firestop Board HILTI CFS-CT B 1S 140/50 - min.
density 140 kg/m
3
+ Firestop acrylic sealant HILTI CFS-S ACR or equivalent)
4
Overplating strip (e.g. Supalux-S, th. 15 mm)*
5
Screw UNI 4x40 mm (span 200 to 250 mm)
6
Spacing strip (e.g. Supalux-S, th. 12 mm, width 40 to 50 mm)
7
M8 bolt assemply (bolt M8x105 mm, 2 pcs large washer M8, nut M8)
X
A
A
≥ 1
00
A-A
X
≥ 100
When installing a flange, overplating
strip is not installed.
Examples of anchors to the fire dividing
construction see. chapter 6.5. and 6.6.
In case of installation damper tightly above the floor,
must be joint between damper body and floor max.
75 mm and must be completely filled with gypsum.
Each Damper must be suitably supported in each
corner front and rear with temporary block-work,
temporary steel supports or similar, until gypsum
has fully hardened.
Содержание SEDM-L
Страница 1: ......
Страница 12: ...12 Dimensions...
Страница 13: ...13 A A 30 A B 17 10 10 X A A Detail X Detail Y B B B B Y...
Страница 14: ...14...
Страница 19: ...19...
Страница 20: ...20 X Detail X Position 1 SEDM L 2 Flange Detail X Detail Y Detail Y Y...
Страница 24: ...24...
Страница 25: ...25 100 Mortar or gypsum EIS 90 26 100 Ablative Coated Batt EIS 120 27 100 Ablative Coated Batt EIS 120 28...