6.
Adjust position of the center-link cylinder (A) with the
reel up and reel down switches on the GSL until the
hook is positioned above the header attachment pin.
IMPORTANT:
Hook release must be down to enable self-locking
mechanism. If the release is open (up), manually
push it down after hook engages header pin.
7.
Lower center-link (A) onto the header with reel down
switch until it locks into position (hook release [B]
is down).
8.
Check that center-link is locked onto header by
pressing the reel up switch on the GSL.
Figure 3.73: Hydraulic Center-Link
CAUTION
Check to be sure all bystanders have cleared the area.
9.
Press the header up switch (A) to raise header to
maximum height.
NOTE:
If one end of the header does
NOT
fully rise, rephase
the lift cylinders as follows:
a.
Press and hold the header up switch until both
cylinders stop moving.
b.
Continue to hold the switch for 3–4 seconds.
Cylinders are now phased.
NOTE:
It may be necessary to repeat this procedure if
there is air in the system.
Figure 3.74: GSL
147764
41