Lucent Technologies Lineage
®
2000 ECS Battery Plant J855003D-3
Issue 5 January 1999
Maintenance 5 - 7
LVD/Fuse Board
(CP5)
Replacement
Procedure: (Refer to Figure 4-4)
1. Open distribution panel.
2. Unplug the following connectors from the LVD/Fuse
Board. Leave the cables dressed.
P502 from J502
P506 from J506
P501 from J501
P504 from J504
Quick Connect from E501
3. Remove the cover over the LVD/Fuse Board and then
remove the insulated standoffs to free the board.
4. Set jumpers J505.1 and J505.2 on replacement LVD/Fuse
Board per J85500D-1 drawing for desired disconnect
voltage.
5. Mount the replacement board to the distributionpanel
using the hardware from Step 3.
6. Reconnect the following connectors:
P502 to J502
P506 to J506
P501 to J501
P504 to J504
Quick Connect to E501
7. Close distribution panel.
Spare Parts
The following equipment may be ordered as spare parts. For
exact ordering codes, refer to recommended spares information
in Section 3 or on the J85500D-3 drawing.
•
Rectifiers and fans
•
LVD/Fuse Board
•
Fuses (F1 to F12)
•
Load Circuit Breakers (CB1 to CB42)
•
Controller Circuit Packs (e.g. 113A/CU. Refer to the
Controller manual for details on spare controller circuit
packs.)