- Instruction Manual for ESS R050096 -
36
◼
This is Battery Setup page.
①③
•
Start =30%---It indicates that the Generator will
start when the Battery capacity is less than 30%
in the condition of
•
Off-grid mode.
•
A= 40A---It indicates the Current that the
Generator charges the Battery after started.
•
Gen Charge---The Switch that the Generator
charges the Battery.
•
Gen Signal ---It indicates whether the
Generator's ATS signal is on or off.
•
Gen Max Run Time---It indicates the longest
time Generator can run in one day, when time
is up, the Generator will be turned off. 24H
means that it does not shut down all the time.
•
Gen Down time---It indicates the delay time of
the Generator to shut down after it has reached
the running time.
◼
This is Grid Charge, you need select.
②
•
Start =30%---no use, for customization.
•
A=40A---It indicates the Current that the Grid
charges the Battery.
•
Grid Charge---The Switch that the Grid charges
the Battery.
•
Grid Signal---Disable.
Lithium Mode--This is BMS protocol (setting 00).
Shutdown 10%--It indicates the inverter will shut down
if the SOC below this value.
Low Batt 20% --It indicates the inverter will alarm if the
SOC below this value.
Restart 40% --It indicates the restart level when
inverter shutdown.
This is Battery 4 stages charge voltage.
①
This is for professional installers, you can hold default
if you do not know.
②
Shutdown 41V--The inverter will shut down if the
Voltage below this value.
Low Batt 45V --The inverter will alarm if the Voltage
below this value.
③
Restart 52V --Restart level when inverter shutdown.