Pre-Installation and Site Preparation Guide
Page 34 of 46
Loring Smart Roast Proprietary – This document is controlled by
Document Control. By printing this document, it will become a “Reference” copy.
Users are responsible for verifying that it is the latest revision available.
1008236 Rev B
Next Steps
Site Preparation Checklist
After confirming the shipping date with Loring, the customer should:
1. Review the
Assembly and Installation Guide
and the
Mechanical Interface Control Documents
(MICDs), available from Loring.
2. Provide the roaster model’s
Pre-Installation Guide
, the
Assembly and Installation Guide
, a copy
of the customer’s completed
Product Specification Form
, and the
Mechanical Interface Control
Document
drawings to the licensed contractor responsible for roaster assembly and installation.
Use the following informal checklist to ensure that the site is fully prepared:
Building meets footprint and clearance requirements for selected roaster model
Building doorways, elevators and corridors can accommodate the roaster
Roaster location is clearly marked
Stack hookup locations exist and are marked
Site Detail/Construction Drawings are completed, accurate, and available
Destoner position has been determined and marked, if applicable
Local code requirements are known, and have been addressed
Required permits have been obtained
Both the moving equipment and the final installation location can handle system weight
Air, Gas, and Electric Utilities have been measured and verified to be within required ranges