Page 21

NOTE –

 

For  horizontal  applications  in  high  humidity  ar-

eas, remove the downflow rail closest to the drain pan. To 

remove rail, remove screw from rail at back of unit and at 

cabinet support rail. Remove downflow rail then replace 

screws. Also, seal around the exiting drain pipe, liquid and 

suction lines to prevent infiltration of humid air.

10 -  Knock out drain seal plate from access door. Secure 

plate to cabinet front flange with screw provided.

11 - Flip access door and replace it on the unit.
12 - 

 Set  unit  so  that  it  is  sloped  1/4ʺ  toward  the  drain 

pan end of the unit. Connect return and supply air 

plenums as required using sheet metal screws.

13 -  If suspending the unit, it must be supported along the 

entire length of the cabinet. If using chain or strap, 

use a piece of angle iron or sheet metal attached to 

the unit (either above or below) so that the full length 

of the cabinet is supported. Use securing screws no 

longer than 1/2ʺ to avoid damage to coil or filter, as 

illustrated in figure 13. Connect return and supply 

air plenums as required using sheet metal screws.

RIGHT-HAND DISCHARGE

1 -   Determine which plugs are required for drain line 

connections. 

2 -   With access door removed, remove drain line plugs 

to install drain lines. 

3 - 

 Set unit so that it is sloped toward the upflow drain 

pan end of the unit and level from front to back of 

unit (see figure 7). 

4 - 

The horizontal configuration is shown in figure 2.

Drains

AIR FLOW

PLUGS

RIGHT

HAND DRAINS

FIGURE 16

. Right-Hand Discharge Configuration

5 -   If the unit is suspended, the entire length of the 

cabinet must be supported. If you use a chain or 

strap, use a piece of angle iron or sheet metal 

attached to the unit (either above or below) to 

support the length of the cabinet. Use securing 

screws no longer than 1/2 inch to avoid damaging 

the  coil  or  filter.  See  figure  13.  Use  sheet  metal 

screws to connect the return and supply air plenums 

as required.

DOWNFLOW APPLICATION

NOTE

 – 

If downflow application is required, separately or-

der kit number Y9658 (-018 through -030) or Y9659 (-036 

through  -060)  and  install  per  kit’s  instructions. Also  use 

metal or class I supply and return air plenums.
Use the installation instruction provided with the downflow kit. 

 IMPORTANT

If electric heat section with circuit breakers (ECBA25) is 

installed in a CBA25UHV unit in a downflow application, 

the circuit breakers must be rotated 180° to the UP 

position. See ECBA25 installation instructions for more 

details.

HORIZONTAL DRAIN PAN 

(REMOVE FROM UNIT)

UP-LOAD /

DOWNFLOW

DRAIN PAN

FIGURE 17

. Downflow Discharge Position

Combustible Flooring Base 

COMBUSTIBLE FLOOR

ADDITIVE BASE

PROPERLY SIZED

FLOOR OPENING

AIR

HANDER

UNIT

FIGURE 18

. Downflow Combustible Flooring Base

1 - 

 For  downflow  installation  on  combustible  flooring, 

an additive base must be used as illustrated in figure 

18.  See  CBA25UHV  Engineering  Handbook  for 

downflow  combustible  flooring  base  kits  available 

for this air handler. 

2 -   Cut an opening appropriately sized for combustible 

base. Base dimensions are illustrated in figure 10. 

After opening has been cut, set the additive base 

into opening. Connect outlet air plenum to the 

additive base. Set the unit on the additive base so 

flanges of the unit drop into the base opening and 

seal against the insulation strips. The unit is now 

locked in place. Install return air plenum and secure 

with sheet metal screws.

Содержание CBA25UH Series

Страница 1: ...UHV Unit Dimensions Upflow inches mm 2 Specifications and Electrical Data 3 Model Number Identification 4 Adjusting the BDC3 Blower Control 4 Adjusting the Blower Speed 4 Blower Data 6 Application 10...

Страница 2: ...3 1 2 89 PIPING PLATE 4 3 4 121 4 3 8 111 2 3 8 60 CONDENSATE DRAINS 2 Upflow and Downflow SUCTION LINE CONDENSATE DRAIN PIPING PLATE 3 2 1 4 x 3 3 4 Dimensions 018 024 030 036 042 048 060 in mm in mm...

Страница 3: ...6 Nominal tonnage 1 5 2 2 5 3 Connections Suction Vapor line o d in sweat 3 4 3 4 3 4 7 8 Liquid line o d in sweat 3 8 3 8 3 8 3 8 Condensate in fpt 2 3 4 2 3 4 2 3 4 2 3 4 Indoor Coil Net face area f...

Страница 4: ...e speed motor that is capable of maintaining a spec ified CFM throughout the external static range A particu lar CFM can be obtained by positioning jumpers COOL HEAT and ADJUST on the BDC3 control The...

Страница 5: ...example that the normal adjustment setting for heat speed position 4 is 1000 CFM The adjustment setting for that position is 1080 CFM and for the adjust ment setting is 910 CFM After the adjustment s...

Страница 6: ...fm cfm 450 670 900 1120 340 450 650 770 450 670 900 1120 NORM 420 620 820 1050 300 400 600 700 420 620 820 1050 390 570 750 915 280 390 500 650 390 570 750 915 NOTES The effect of static pressure filt...

Страница 7: ...speed setting Lennox Harmony III Zoning System applications minimum blower speed is 450 cfm BLOWER DATA CBA25UHV 048 BLOWER PERFORMANCE 0 through 0 80 in w g External Static Pressure Range ADJUST Jump...

Страница 8: ...On Demand 0 VAC High 60 65 70 PRECISION MODE operates independent of a Y1 thermostat demand Normal Operation 1 On On On Acceptable 24 VAC High 100 midity is greater than set point Dehumidification Cal...

Страница 9: ...Demand 0 VAC High 60 65 70 Dehumidification Call ONLY 1 On On On On Demand 0 VAC High 60 65 70 midity setpoint by allowing the room stat setpoint Jumpers at indoor unit with a two stage outdoor unit W...

Страница 10: ...pening The electric heat control arrangement is detailed in the electric heat section of this manual TRANSFORMER All CBA25UHV series units use a single line voltage to 24VAC transformer mounted in the...

Страница 11: ...alumi num tubes fitted with ripple edged aluminum fins An ex pansion valve feeds multiple parallel circuits through the coils The coil is designed to easily slide out of the unit cabinet PLASTIC DRAIN...

Страница 12: ...Minimum Circuit Ampacity 3 Maximum Overcurrent Protection Volt kW 1 Btuh 5 kW ECBA25 5 16Y36 Terminal Block ECBA25 5CB 16Y39 30A Circuit Breaker 208 3 6 12 300 3 9 27 30 220 4 0 13 800 3 9 28 30 230 4...

Страница 13: ...20 8 0 27 500 3 9 51 60 230 8 8 30 000 3 9 53 60 240 9 6 32 700 3 9 55 60 12 5 kW ECBA25 12 5CB 16Y43 1 50A and 1 25A Circuit Breaker 208 9 4 32 000 3 9 42 19 4 45 4 20 61 70 220 10 5 35 800 3 9 45 20...

Страница 14: ...220 8 0 27 500 3 9 51 60 230 8 8 30 000 3 9 53 60 240 9 6 32 700 3 9 55 60 12 5 kW ECBA25 12 5CB 16Y43 1 50A and 1 25A Circuit Breaker 208 9 4 32 000 3 9 42 19 4 45 4 20 61 70 220 10 5 35 800 3 9 45 2...

Страница 15: ...2 60 220 8 0 27 500 6 9 54 60 230 8 8 30 000 6 9 57 60 240 9 6 32 700 6 9 59 60 12 5 kW ECBA25 12 5CB 16Y43 1 50A and 1 25A Circuit Breaker 208 9 4 32 000 6 9 46 19 50 4 20 65 70 220 10 5 35 800 6 9 4...

Страница 16: ...50A and 1 25A Circuit Breaker 208 9 4 32 000 6 9 46 19 50 4 20 65 70 220 10 5 35 800 6 9 48 20 50 4 20 68 70 230 11 5 39 200 6 9 50 21 50 25 71 80 240 12 5 42 600 6 9 52 22 4 60 25 74 80 15 kW ECBA25...

Страница 17: ...to Install Heat Element 5 Slide the electric heat section into the air handler Be careful that the heating elements do not rub against the sheet metal opening when they slide into the air handler The...

Страница 18: ...ity and maximum overcurrent protec tion size Select the proper supply circuit conductors in accordance with tables 310 16 and 310 17 in the National Electric Code ANSI NFPA No 70 or tables 1 through 4...

Страница 19: ...oom temperature 2 Check the heat pump and the heat section for normal operation 3 Set the thermostat to desired setting 4 Affix the wiring diagram sticker to air handler scroll aligned with circuit br...

Страница 20: ...pen and free of any debris Also check to make sure that no debris has fallen into the drain pan during installation that may plug up the drain opening 4 Rotate drain pan 180 front to back and install...

Страница 21: ...orted If you use a chain or strap use a piece of angle iron or sheet metal attached to the unit either above or below to support the length of the cabinet Use securing screws no longer than 1 2 inch t...

Страница 22: ...t damage injury or death When using a high pressure gas such as nitrogen to pressurize a refrigeration or air conditioning system use a regulator that can control the pressure down to 1 or 2 psig 6 9...

Страница 23: ...QUIREMENTS NOTE REFRIGERANT LINE SETS SHOULD BE ROUTED TO ALLOW FILTER ACCESSIBILITY NOTE CBA25UHV SERIES UNITS USE NITROGEN OR DRY AIR AS A HOLDING CHARGE IF THERE IS NO PRESSURE WHEN THE RUBBER PLUG...

Страница 24: ...PER 3 METERS NOTE WHEN A AIR HANDLER IS LOCATED ABOVE A FINISHED SPACE THE SECONDARY DRAIN PAN MUST HAVE A LARGER FOOTPRINT THAN THE AIR HANDLER MAIN DRAIN TO APPROVED DRAIN FOR NEGATIVE PRESSURE COI...

Страница 25: ...ain line after installation 1 Pour several quarts of water into drain pan enough to fill drain trap and line 2 Check to make sure the drain pan is draining completely no leaks are found in drain line...

Страница 26: ...t be drawn from a room where this air handler or any gas fueled appliance i e water heater or carbon monoxide producing device i e wood fireplace is installed Make sure the liquid line and suction lin...

Страница 27: ...ically ground air handler Connect ground wire to ground terminal marked GND Failure to do so can result in death or electrical shock Inspecting and Replacing Filters IMPORTANT Filter access door must...

Страница 28: ...Page 28 Wiring Diagrams FIGURE 24 Typical Wiring Diagram CBA25UHV Air Handler with Electric Heat Variable Speed Motor...

Страница 29: ...Page 29 WARNING USE COPPER CONDUCTORS ONLY FIGURE 25 Low Voltage Connections Variable Speed Motor...

Страница 30: ...tdoor unit being used Have all unused parts and packaging been disposed of Is the filter clean in place and of adequate size Is the wiring neat correct and in accordance with the wiring diagram Is the...

Страница 31: ...they may also be connect ed to a second stage on the subbase HEATING HEAT PUMP When the thermostat calls for heating 24 volts is put on the blower time delay relay coil Then normally open con tacts c...

Страница 32: ...Duct Temperature ___________ THERMOSTAT Adjusted and Programmed Return External Static ______ ______ Total External Static ______ ______ 6 Supply Duct Temperature ___________ Temperature Drop _______...

Страница 33: ...ternal Static ______ ______ 6 6 Supply Duct Temperature ___________ Temperature Drop ___________ TEMPERATURE RISE Heating Mode Return Duct Temperature __________ Supply Duct Temperature __________ Tem...

Отзывы: