Alpin Z300 4 Installation manual
Lehner Lifftechnik GmbH
Installation with a crane:
Fix the 2 attached hooks on the top of the main tower after you have removed the cover from
the tower. Each hook will be fix with 3 bolts. Tight the bolts good. After that you can fix the
strap on the hooks and move the tower to the installation postion. Hold the tower with the crane
as long as you have fixed it with bolts to the concrete floor.
Hooks for the lifting
of the tower