Depth Adjust (Microadjust)
The depth of each wall mount section is controlled by a screw
accessible only after removing LED display from LED housing.
1.
Remove LED display from LED housing. (See Figure 21)
2.
Adjust depth adjustment screw until LED housing is
adjusted to desired depth using T-handle M5 hex key (not
included). (See Figure 21)
3.
Replace LED display into LED housing.
IMPORTANT ! :
It is best to make adjustments in small
increments to prevent any binding or torquing of the
mounts. Be sure to adjust the depth evenly for both sides
of the mounts.
CAUTION:
Over-torquing may cause damage. Do NOT
use a drill to make the depth adjustment.
Figure 21
Fastener Installation Methods
IMPORTANT ! :
See Table 1 for appropriate hardware
and pilot hole sizes for various wall types.
IMPORTANT ! :
The expanse of the LED wall will most
likely mean that attachment of the wall mounts will not all
be in studs. The attachment method will most likely vary
throughout the installation, and more than one of the
various methods outlined here will most likely be used.
Concrete or Concrete Block
1.
Install one UX10X60R anchor (B) into each pilot hole using
a hammer, making sure that the anchor is flush with the wall.
(See Figure 22)
2.
Use one 5/16" x 2-1/2" hex flange head lag bolt (C) and one
5/16" washer (D) through product into each anchor in wall.
(See Figure 22)
NOTE:
5/16" washers (D) may not be necessary if using
adjustment washers (A) to install to wall.
3.
Repeat for remaining pilot holes.