Installation steps
1.
Installation Steps for V and W Transducer Mounting Method
When using V or W method to install transducers, install the two transducers on the same
side of pipeline.
Steps:
1.
Connect the chains and spring.
2.
Lay on enough couplant on the transducer.
3.
Connect the transducers cable.
4.
Enter the application parameters in transmitter to get the XDCR spacing in menu
25.
5.
Install and fix the transducers on the ruler using knurled screws.( note if the
wrong space is applied, the measurement fails or the measurement will have
wrong values)
6.
Fix the transducers using the chains and springs.
7.
Approach the transducers to the pipe by adjusting the knurled screw until the
transducer is pressed slightly onto the pipe.
2 Installation Steps for Z and N Transducer Mounting Method
When using Z or N method to install transducers, install the two transducers respectively on
the opposite sides of pipeline. Installation steps are same as for W and V transducer mounting
method without ruler.
When finishing the installation, it will show as follow:
Top View
XDCR Spacing