21
4.2.3 Removal of side
The installation power breakers must be in the “OFF” position.
Unscrew the screws marked with 1 on the right side of the device.
Pull the lower part of the side (2) towards you and disconnect it from the device’s cover.
4.2.4 Concrete pedestal
The installation (connections above or below ground) routed from the DHW room to the device does
not influence the make of the concrete pedestal.
To ensure greater protection against freezing, installation using an underground cable duct is
recommended.
Installation of the concrete pedestal
The reinforced concrete pedestal must be installed on a suitable buffered base. The recommended
minimal edge thickness of the concrete pedestal is given by the design engineer according to the mass
of the device (chapter 7.2).
WPL-45-K1 HT
WPL-70-K1 HTT and WPL-90-K1 HTT
CAUTION
The device must be screwed on the left and right side through the supporting legs to the
concrete pedestal because of the possibility of stronger gusts of wind.