16
Remark:
It is recommended to always keep the RS-485 cores (pins 2 and 4) accessible
from the ground so the Geovane can be re-configured and updated without
having to dismount it from the met mast.
3.3.1
Cable shielding
It is critical that appropriate shielding is used to reduce EMI. The connection of
the cable shield depends on whether or not the mounting of the Geovane on the
boom is isolated.
If the mounting of the Geovane is isolated (i.e. non-metallic adaptor sleeve), the
cable shield between the Geovane and the data acquisition system must be
applied at both sides.
When the mounting of the Geovane is non-isolated (i.e. metallic adaptor sleeve),
the cable shield between the Geovane and the data acquisition system must be
applied one-sided at the data acquisition device.
Both cases assume that the metallic measurement mast and the data acquisition
system are grounded.