– Installation Guidelines for BioDisc BA, BAx, BB & NB Units 

    Page  6 

1.3.10  BioDisc units must be installed at a level which will allow connection to the incoming drain and a free 

discharge at the system outlet (excepting units with an integral discharge pump). Effluent pumping 
stations are available to lift the discharge to a higher level and/or pump to remote discharge points. 

1.3.11  The unit should be installed so that the bottom lip of the cover is 95mm above local ground level. If 

the unit has to be recessed, measures must be taken to ensure that it cannot be flooded by surface 
water run-off.  

1.3.12  It is essential that all surface water be segregated and excluded from entering the treatment plant. 

1.3.13   BioDisc covers are not suitable for walking on. Where necessary the BioDisc should be fenced off or 

otherwise protected. Maintenance access must be maintained as above. 

1.3.14  The drainage system connecting to the BioDisc must be adequately vented in accordance with the 

Building Regulations. The head of the drainage system should be connected to a stack pipe, open at 
high level, so as to draw foul air from the system and sited with consideration to prevailing wind 
direction. Tile vents & Air admittance valves should not be used as the sole drainage ventilation 
facility, but if this cannot be avoided, the BioDisc should be independently ventilated.  All inspection 
points within the drain system should be sealed so as to enable ventilation at high level. 

1.3.15  An adequate electrical supply must be provided, complying with current electrical regulations. The 

electrical details in Table 1 will enable selection of suitable cable and current overload protection, 
taking into account the distance from the power source to the control panel and any other relevant 
factors. In most cases steel wire armoured (SWA) cable, minimum 1.5sq mm will be suitable, 
selection of the cable is the responsibility of the installing electrician. 

 

 

 

Full Load Current (Amps) 

 

 

BA 

BAx 

BB 

NB 

Motor 

240 volt single phase 

0.52 

0.52 

0.52 

0.52 

415 volt three phase 

0.22 

0.22 

0.22 

0.22 

Integral discharge pump 

240 volt single phase only 

2.2 

2.2 

2.2 

N/A 

Sludge return pump 

240 volt single phase only 

N/A 

N/A 

N/A 

2.2 

 

Table 1 : Electrical Supply Data 

1.3.16  Residual Current Device (RCD) protection is required for BioDisc units fitted with an integral 

discharge pump. RCD protection is not obligatory for BioDisc units without a discharge pump, but is 
suggested as an extra precaution. 

1.3.17  Independent pump stations or any other associated equipment should have a separate power 

supply. 

1.3.18  Proximity to a mains water hose pipe connection point is recommended, for maintenance purposes. 

Such a supply should be connected in accordance with water bylaws and regulations. 

Never leave a

 

hose connected and immersed in sewage.

 

1.3.19  Installation should only be carried out by suitably qualified and experienced contractors in 

accordance with the Health and Safety at Work Act. Electrical work should be carried out by a 
qualified electrician, working to the latest edition of IEE. 

Installation - General 

2.1.1 

When units are installed in unstable ground conditions where movement of the surrounding material 
and/or unit may occur, the connecting pipework should be designed to minimise the risk of damage 
from differential movement of the unit(s) and/or surrounding material. 

2.1.2 

In situations where the excavation will not maintain a vertical wall, it will be necessary to support side 
walls of the excavation (e.g. with suitable trench sheets and bracing systems) to maintain a vertical 
wall from the bottom to the top of the excavation. DO NOT completely remove the shoring system 
until after the back-filling is complete, but before the concrete fully hardens. 

2.1.3 

In areas where the water table is above the bottom of the excavation and/or the excavation is liable 
to flood, the excavation should be de-watered, using suitable pumping equipment, until the 

Содержание BioDisc BA

Страница 1: ...ical connection or if there is no power available to operate the unit then the motor with gearbox must be removed and stored in a dry environment The motor keeps dry by generating its own heat when op...

Страница 2: ...d recommended Please contact Kingspan for details of your local service provider Should you wish to inspect the operation of the equipment please observe all necessary precautions including those list...

Страница 3: ...shire HP22 5EW United Kingdom 07 EN 12566 3 BA BF BioDisc Hydraulic daily load 1 2m day 10m day Material GRP Glass Reinforced Plastic Watertightness water test Pass Structural Calculation Pass Treatme...

Страница 4: ...4 2 Mounting Frame Installation where applicable 10 4 3 Installation of Control Panel 10 4 4 Installation of Integral Discharge Pump where applicable 11 4 5 Installation of Sludge Return Pump where ap...

Страница 5: ...owing points should be considered before installation of the equipment 1 3 2 The discharge must have the consent of the relevant Environmental Regulator 1 3 3 The installation should have Planning and...

Страница 6: ...table selection of the cable is the responsibility of the installing electrician Full Load Current Amps BA BAx BB NB Motor 240 volt single phase 0 52 0 52 0 52 0 52 415 volt three phase 0 22 0 22 0 22...

Страница 7: ...of the unit contains this copy of the Installation Guidelines and a cover key 2 2 2 Excavate a hole of sufficient length and width to accommodate the unit and a minimum of 150mm concrete surround and...

Страница 8: ...red Cable supply to control panel Customer Supply Inlet Pipe Outlet Effluent to Soakaway Ditch Stream etc via Sample Chamber if fitted Control Panel Refer to Section 6 for position G L 450mm Inlet Inv...

Страница 9: ...l as described in Section 3 2 4 6 Continue to back fill with concrete wet site or free flowing granular material dry site up to ground level The finished surface should be 95 mm minimum lower than the...

Страница 10: ...et 4 2 2 Allow 350mm minimum clearance from finished ground level to the bottom of the panel 4 3 Installation of Control Panel Figure 1 Control Panel 4 3 1 Remove the four screws on the front of the p...

Страница 11: ...applicable 4 5 1 Using a suitable M20 gland feed the integral discharge pump power cable through Gland Hole 3 Figure 1 and terminate to connection 3 4 TB2 following the guide on Table 2 4 5 2 Set the...

Страница 12: ...crewdriver push switch 10 to the ON position 4 8 Installation of High Level Alarm where applicable 4 8 1 Remove the link in the terminal blocks between connections 11 12 TB6 before inserting cables Us...

Страница 13: ...owing the procedure in the Owners Handbook and leave the unit running even if there is no sewage being fed into the plant 7 1 4 If the unit has been installed with no operational power supply then rem...

Отзывы: