![Kewtech KT77 Скачать руководство пользователя страница 24](http://html1.mh-extra.com/html/kewtech/kt77/kt77_instruction-manual_1960003024.webp)
46
www.kewtechcorp.com
47
www.kewtechcorp.com
www.kewtechcorp.com
re –Test period
Use the cursor keys to select RE-TEST PERIOD and then press the ENTER
key to choose a re-test period.
Complete the rest of ENTER APPLIANCE DETAILS as normal and move on to
the next stage in the test process.
note for paTguard users
Re-test periods are downloaded with test results and are compared
with re-test periods of existing Assets on PATGuard or used as the
re-test period for new Assets. This is to ensure that re-test periods
are ‘synchronized’ across the PAT system.
for pat Manager users re-test periods are downloaded and appear
in the test sheet reports as entered in the KT77
HOW TO PERFORM MANUAL TESTS
----RE-TEST PERIOD----
NOT REQUIRED
1 MONTH
3 MONTHS
6 MONTHS
12 MONTHS
24 MONHTS
48 MONTHS
OTHER...
select Manual Test
Use the appropriate number key from the table to select a specific test or
use the cursor to highlight the desired option.
performing a Manual Test
After selecting the appropriate test the tester displays a screen from which
you can set test parameters.
The user can change an individual setting when the parameter is shown in
inverse video. Use the left and right cursor keys to highlight a field on the
display. Then use the up & down cursor keys to change the variable in the
selected field.
Isolated Test
This is a normal Earth Bond Test where the EUT is plugged into the Tester
power socket and the Earth Bond lead is connected to the EUT. This is the
default test.
During this stage of the test a large icon showing the earth bond probe
attached to a mains power appliance will be displayed.
earth bond limit Calculator
Earth Bond tests have an additional Fast Key; LIMIT CALC. Selecting this
enables the User to set an accurate Earth Bond Test limit by specifying the
cable parameters.
In – situ Touch leakage Test
The Touch Leakage Test can be performed without powering down the EUT
and plugging it into the tester power socket. The only connection the User
is required to make is to connect the Earth Bond Test lead to the exposed
metal work of the EUT and then perform the test.