7.2
Connecting split-core current transformers
Fig. 7-7: Energy meter with plug, bottom view
Pin
Phase
Wire
1
L1
S1 (red)
2
S2 (black)
3
L2
S1 (red)
4
S2 (black)
5
L3
S1 (red)
6
S2 (black)
Caution
Damage to property!
●
Only the included split-core current transformers may be connected.
●
Always connect the split-core current transformers to the device first and
then fold over the phase conductors.
●
Make sure that the phases are each correctly assigned. Otherwise, the
device will return false measured values.
To connect the split-core current transformers, proceed as follows:
1) Connect the connection cable of the split-core current transformers to
the 6-pin plug (scope of delivery) according to the connection overview.
2) Connect the connection plug to the energy meter.
3) Open split-core current transformers for L1, place around phase conduc-
tor L1 and close again until it audibly latches. Observe the direction of
the arrow!
4) If present: Repeat steps for phase conductors L2 and L3.
The split-core current transformers are connected.
Содержание KeContact E10
Страница 1: ...KeContact E10 Energy meter Installation manual V 1 00 Original instructions...
Страница 30: ...E10 Declaration of conformity V1 00 30 KEBA 2023 15 Declaration of conformity...
Страница 31: ...E10 Declaration of conformity V1 00 31 KEBA 2023...
Страница 33: ......
Страница 34: ...KEBA Energy Automation GmbH Reindlstra e 51 4040 Linz Austria www keba com...