7
CHAMANUAL 0917
KAM CONTROLS, INC.
Remove all the protective packaging materials , and ensure that the CHA™ sensor was not damaged
during transit.
PRIOR TO INSTALLATION
I N S TA L L AT I O N
Do not install the CHA in direct sunlight
Ensure there is no entrained air in the line or excessive levels
of organic compounds such as rouge.
CHA should be installed after a minimum of 4 pipe diameters
of straight run to reduce flow turbulence. Fig. 3-1
The CHA should be installed on a vertical line. If the unit
must be intalled on a horizontal line, it should be at 3 or 9
o'clock position. Fig. 3-2
The KAM CHA probe must be oriented so that the flow
indicator is parallel to the flow direction of the pipe to
enable flow through the measurement window. Fig. 3-3
Flow
indicator
INSTALLATION DOs and DONTs
MINIMUM 4 PIPE
DIAMETERS BEFORE
METER
MINIMUM 4 PIPE
DIAMETERS BEFORE
METER
FIG. 3-1
VERTICAL INSTALLATION
FIG. 3-2
HORIZONTAL INSTALLATION
FIG. 3-3
3 O'clock
9 O'clock
NOTE: Installation at the 12 O'clock or 6 O'clock position
could result in the accumulation of fluid contaminents
(dirt, etc.) on the lenses, causing measurement malfunc-
tion.