Use r ma nual Ka bola B-serie, 1-4-2005 

9

 

Figure  7 

Figure  6 

4.  Connect point 2 of the connector to point L1 of the room thermostat. 

 

Atte ntion:  

The core diameter of the connections mentioned above must be between 1 and 1,5mm².   

The wires should be suitable for the voltage used. 
 

Conne cting the circulation pump

 (see figure 5 and electrical scheme in appendix C) 

1. 

Connect the pump to points 3 and 4 of the connector. 

2. 

Connect point 5 to the ground connection on the pump 

3. 

Replace the cover of the main connector. 

 
 

Ele ctrica l installation 24 Volts DC 
 
Wa rning:  

Never change the + pole with – pole 

on the battery (See figure 6). 
 
1. 

The connection of the room thermostat 

is identical to the connection for the 230 Volts 
version. Use figure 6 instead of figure 5. 
2. 

Connect the circulation pump to points 

3 and 4 of the main connector. 
3. 

The core diameter of the wires to points 

5 and 6 of the connector should conform to the 
values in  
 

table 1. 

 
Table 1 

Distance to the battery 

Core diameter 

±  6 metres 

6 mm² 

±  15 metres 

10 mm² 

 

4.1.5  Filling the central heating system 

 

The pressure in the system should: 
• 

Never be lower than 0,5 bar cold; 

• 

Never be higher than 2,5 bar hot; 

 
Follow the procedure listed below for filling the CH-system (see figure 7) 
1. 

Switch off the boiler 

2. 

Turn the coupling nut below the pressure indicator to loosen it; 

3. 

Pull the hose connection a little downwards; 

4. 

Connect the hose with a hose clamp to the connection. 

5. 

Fill the system slowly with water, until the pressure indicator indicates 

 

a pressure of 2 bar. 

6. 

Fasten the coupling nut; 

7. 

Bleed the CH-system 

8. 

If necessary, fill with water again up to 2 bar of pressure. 

9. 

Switch on the boiler and let the pump run for about 5 minutes. 

10. 

Switch off the boiler. 

11. 

Check the water pressure, if it is too low, repeat steps 5 through to 10; 

12. 

Remove the hose. 

 

Hint:  

The CH-system can be filled with cooling fluid, suited for CH-systems (pH-value 8.5). 

 
 
 

Содержание B-8

Страница 1: ......

Страница 2: ...ay Hint This gives the user suggestions and advises to facilitate the execution of certain tasks Attention Additional information is supplied to the user and possible problems are indicated Warning Wa...

Страница 3: ...al heating system 7 4 1 3 Flue gas outlet 7 4 1 4 Electrical installation 8 4 1 5 Filling the central heating system 9 4 1 6 Mounting the burner 10 4 1 7 Connecting the oil filter and oil burner 11 4...

Страница 4: ...ation These boilers are not designed for direct heating of the rooms in which they are installed 1 3 Product description The B Series boilers heat the central heating water by means of a pressure jet...

Страница 5: ...be complied with when operating the B Series boilers Measures for a safe installation Don t store any flammable and or gaseous products in the room where the boiler is installed to avoid explosions a...

Страница 6: ...burner Store the boiler standing up Store the boiler on a firm horizontal base 4 Installing and preparing for first use In this chapter you will find directions and hints for a correct placement and f...

Страница 7: ...arts where contact with human body parts is possible For a correct flue gas outlet the following points need to be observed Use the proper length diameter dimensions use a diameter equal to the diamet...

Страница 8: ...5 elbows of 90 The maximum allowed length is 10 metres Every elbow of 90 counts as 1 metre Outside use double walled chimney pipe Hint To reduce the noise resulting from flames it is wise to install...

Страница 9: ...res to points 5 and 6 of the connector should conform to the values in table 1 Table 1 Distance to the battery Core diameter 6 metres 6 mm 15 metres 10 mm 4 1 5 Filling the central heating system The...

Страница 10: ...a B12 you need to saw an extra piece off the flange The mounting of the burner is done in the following way 1 Place the nut for the flange bolt in the dedicated position and place the gasket 2 Mount...

Страница 11: ...nnect the fuel line from the tank to the filter 5A The fuel line must have a outer diameter of 8mm and must be made from copper or steel The fuel has to be connected directly to the oil tank Correct f...

Страница 12: ...button 8 and return to 5 4 repeat if necessary 5 9 Close the bleeding 3B when only oil and no bubbles come out of the hose Attention The oil burner is tested by the manufacturer not adjusted The adjus...

Страница 13: ...pes with a thin metal strip Attention Don t use any aggressive solvents like thinner or gasoline 1 9 Clean the boiler with a vacuum cleaner 1 10 Replace the boiler top if necessary use a new gasket 1...

Страница 14: ...ection 1 1 1 5 4 1 1 2 2 2 2 IP value 50 11 Burner 230 V 24 V 2 B009 3 C012 2 B010 3 C013 2 B011 3 C014 2 B012 3 C015 2 B013 3 C016 2 B014 3 C017 2 B014 2 B016 2 B017 Nozzle 60 0 30 0 40 0 50 0 85 1 0...

Страница 15: ...ation pump 13 Seal Two 1 or bigger 14 Knee inner x outer thread Different per type 1x1 1 x1 or 1 x1 15 Pressure valve pressure gauge fill drain cock 16 T connection 1 x x1 Only for B 12 17 Fire inspec...

Страница 16: ...User manual Kabola B serie 1 4 2005 16 Appendix C Electrical diagram B8 B70 230V...

Страница 17: ...User manual Kabola B serie 1 4 2005 17 Appendix D Electrical diagram B80 B100 230V...

Страница 18: ...User manual Kabola B serie 1 4 2005 18 Appendix E Electrical diagram B8 B45 24V...

Страница 19: ...f flame protection Flame protection defect photo cell Replace flame protection Burner starts pulsing Flue glass flow interrupted Clear chimney opening Boiler dirty Clean boiler Oil supply interrupted...

Страница 20: ...User manual Kabola B serie 1 4 2005 20 Appendix G CE declaration...