Rev - D
Page 8 of 9
7)
Make any necessary adjustments.
8)
Install the Six, 6” wide steel cleats beneath each of the six lines, see Figure 8 & 9. It is
recommended that the cleats be installed at a height of at least 7 ft above the floor.
Figure 8: Standard Building Attachment - For Metal Structure and Wood Blocking
Figure 9: Standard Building Attachment on Fixed End - For Solid Concrete Walls
(Double Expansion Shield Not Provided)
9)
Lower the net by releasing each hoisting line from the cam cleat. Before removing the net go
back and cut off any excess rope from the hoisting line. Tie a knot in the very end of each
line to prevent the line from accidentally passing through the pulley block.
10)
Remove the net and store in a suitable container. See optional net storage cart (TENINJA-CART).
11)
Gather all lines and hang them from their respective wall cleat.