USER MANUAL NG
Start-Up
(1) Previous Checkup
a) Is the machine leveled?
b) Voltage and frequency are the same as those on the nameplate?
c) Are the discharges connected and operating?
d) Will the ambient temperature and water temperature remain in the following range?
ROOM
WATER
MAXIMUM
109º F / 43º C
95º F / 35ºC
MINIMUM
41ºF /5ºC
41º F / 5ºC
e) Is water pressure appropriate?
MINIMUM
14 psi (1 Bar / 0.1 Mpa)
MAXIMUM
85 psi (6 Bar / 0.6 Mpa)
NOTE: In case input water pressure is higher than 85 psi (6 bar / 0.6 Mpa), install a pressure regulator.
(2) Start-Up
Once the installation instructions are followed (ventilation, site conditions, temperatures, water quality, etc.),
proceed as follows:
1) Open the water inlet. Verify the no existence of leakages.
2) Open the door and remove the protection elements that are inserted behind the curtain.
3) Connect the machine to the electrical network.
4) Push the main switch placed on the front side.
5) Verify that there are no vibrations or frictions on the elements.
6) Verify that the curtain moves freely.
7) Verify that the nozzles send the water to the evaporator on the right direction (even spread).
8) After 10 minutes, verify that the water container has no leakages through the maximum level
overflow pipe.
The technical installer shall invoice traveling expenses, labour cost hours and materials used.
6