PM605KT/PM605KT-B Technical documentation
31
6. Installation
MDR installation
Safety precautions
Preparation Before Installation
Check product
Installation
Maintenance
Appendix
Original notice - A1.1
6-4.
MDR installation with
M10 shaft on free side
MDR installation with M10 shaft on free side
Ø 10,4 mm
Idle end cap side
Frame hole
Screw M10x20
2
8
15
Insert the cable-side shaft into the chassis hole.
Prevent risk of shearing or sticking the cable.
CAUTION
Make sure the conveyor
frame is grounded.
Position the end cap shaft in front of the chassis hole and fix with M10 screws.
Ø
10,4 mm
M10
Frame hole ø10,4mm
MBK-0K1
Tightening torque
27Nm
1
2
Cable diameter : 5.5mm
The minimum bend internal radius is 16.5mm.
Reference
Screw
SP-M10-20