3. A depth gage is provided with the machine for checking the
oil level through the hole in the table that is capped with a hex
screw (Figure 10 and 10A). The overall length of the gage pin
should be set to equal the thickness of the machine table
(Figure 10B). Set pin to bottom of table and tighten setscrew
on side of gage (Figure 10C). The oil level line marked on the
gage pin is 1/16” above the bottom of the table.
4. In the center hole of the table is a 7/16”-14 set screw. This was
installed during shipping of the machine to keep any debris out
of the hole. Remove set screw and discard.
FILL COOLANT TANK
Open front access door and slide coolant tank out of machine
(Figure 11). Pour one quart of
(P/N: 794-8011-40)
Coolant Additive
into the tank and add water to within approximately one inch of the
top. Slide coolant tank back into machine. Direct coolant drain hose
to the inside of the tank. After machine is wired, turn on coolant
pump and set flow by turning valve located outside the sheet metal
coolant shroud (Figure 12).
Figure 10C
Figure 10A
Figure 10B
Figure 10
CAUTION:
Excessive buildup of
grinding sludge in the
coolant may cause
premature failure of
the coolant pump.
Clean out coolant tank
every 25 flywheels or
more frequently as
needed.