3.1  Initial Inspection

IET instruments receive a careful mechanical and 

electrical inspection before shipment.  Upon receipt, 

verify that the contents are intact and as ordered.  

The instrument should then be given a visual and 

operational inspection.

If any shipping damage is found, contact the carrier 

and IET Labs.  If any operational problems are en-

countered, contact IET Labs and refer to the warranty 

at the beginning of this manual.

Save all original packing material for convenience 

in case shipping of the instrument should become 

necessary.

3.2  Installation

For a rack mounted model, installation in a 19 inch 

rack may be made using the slots in the rack mount-

ing ears.  A mounting location that does not expose 

the unit to excessive heat is recommended. For bench 

models there is no required installation.  

Since this is a high accuracy instrument, it is rec-

ommended that a space be provided that would not 

expose it to mechanical abuse and keep it maintained 

at laboratory standard temperatures near 23ºC.

3.3  Repackaging for Shipment

If the instrument is to be returned to IET Labs, contact 

the Service Department at the number or address, 

shown on the front cover of this manual, to obtain a 

“Returned Material Authorization” (RMA) number 

and any special shipping instructions or assistance.  

Proceed as follows:

1.  Attach a tag to the instrument identifying the 

owner and indicate the service or repair to be 

accomplished.  Include the model number, 

the full serial number of the instrument, the 

RMA number, and shipping address.

2.  Wrap  the  instrument  in  heavy  paper  or 

plastic.

3.  Protect the front panel and any other protru-

sions with cardboard or foam padding.

4.  Place  instrument  in  original  container  or 

equally substantial heavy carton.

5.  Use  packing  material  around  all  sides  of 

instrument.

6.  Seal with strong tape or bands.

7.  Mark  shipping  container  “DELICATE 

INSTRUMENT,” “FRAGILE,” etc.

3.4  Storage

If this instrument is to be stored for any lengthy period 

of time, it should be sealed in plastic and stored in a 

dry location.  It should not be subjected to temperature 

extremes beyond the specifications.  Extended expo

-

sure to such temperatures can result in an irreversible 

change in resistance, and require recalibration.

Содержание RS-925D

Страница 1: ...www ietlabs com IET LABS INC Email info ietlabs com Precision instruments for test and measurement RS 925D Resistance Standard User and Service Manual Copyright 2014 IET Labs Inc Visit www ietlabs com...

Страница 2: ...ruments for test and measurement IET Model RS 925D This RS 925D is the IET Labs version of the original esi RS 925D Decade Resistance Standard The IET unit is updated and features a number of signific...

Страница 3: ...i...

Страница 4: ...ii...

Страница 5: ...ermal emf Considerations 5 4 3 Dial Setting 6 4 4 Rheostat Operation 6 4 5 Power Considerations 6 4 6 Environmental Conditions 7 4 7 Switch Conditioning 7 4 8 Meter Shunt Applications 7 4 9 Kelvin Bri...

Страница 6: ...al Operating Guide Affixed to Unit 3 Figure 4 1 Rheostat Dial 6 Figure 4 2 Rheostat Schematic 6 Figure 4 3 Kelvin Bridge Connections 7 Table 5 1 Trimming Potentiometers 11 Figure 5 1 Typical Trimmer B...

Страница 7: ...e reading The RS 925D Resistance Standard employs com pletely enclosed dust tight very low contact resistance switches They feature solid silver alloy contacts and quadruple leaf silver alloy wipers w...

Страница 8: ...1 10 ppm 5 ppm typical 10 k 100 k 10 mA 5 W 3 0 1 100 k 1 M 3 mA 2 000 V peak 3 0 1 Wiring and switch resistance NA 50 C 0 2 W NA At 23 C true ohm measurement 30 70 RH absolute reading SI traceable N...

Страница 9: ...r Decade positions Resistor type whichever applies fi rst 100 division 20 resolution 10 m 2 A NA 20 1 20 ppm 0 5 m Continuous Rheostat 1 m 10 m 2 A NA 20 1 11 positions 0 10 Resistance wire 10 m 100 m...

Страница 10: ...ard temperatures near 23 C 3 3 Repackaging for Shipment If the instrument is to be returned to IET Labs contact the Service Department at the number or address shown on the front cover of this manual...

Страница 11: ...sistance or low resistance increments are important care must be taken in connecting to the terminals of the decade box In particular to keep contact resistance to a mini mum 4 terminal connections sh...

Страница 12: ...etting in the next decade into consideration To get 1 000 for example the switches should be set to show 0 9 10 0 Since the highest decade has an additional 11 po sition resistance values of over 1 2...

Страница 13: ...connected to the current source 2 Determine the current by the ratio of the mea sured voltage to the known resistance Using the 4 terminal technique helps avoid errors caused by the voltage drops in t...

Страница 14: ...e housing 2 Remove any dust or debris using optical grade dry compressed air or a clean brush 3 Replace the housing and reattach the 4 hous ing screws The front panel should be periodically cleaned to...

Страница 15: ...follow ing models HATS LR HATS Y SRL Series The 1 and 10 transfer standards are optional and are only used to take advantage if desired of the trimmability of these two decades Precision resistance me...

Страница 16: ...TION The RS 925D front panel should be connected to the test instrument s guard point 5 4 2 Trimming Procedure To trim any resistances proceed as follows 1 Stabilize RS 925D at laboratory temperature...

Страница 17: ...er Designation All decades but 1 k Potentiometer Designation 1 k decade 1 T0 T1 2 T1 T2 3 T2 T3 4 T3 T4 5 T4 T5 6 T5 T6 7 T6 T7 8 T7 T8 9 T8 T9 10 T9 T10 11 T10 1 M steps only Table 5 1 Trimming Poten...

Страница 18: ...HARS 4000 LX 0 1 100 m step Decade Switch Assembly Not Shown HARS 4000 LX 1 1 step Decade Switch Assembly Not Shown HARS 4000 LX 10 10 step Decade Switch Assembly Not Shown HARS 4000 LX 100 100 step...

Страница 19: ......

Отзывы: