SECTION FOUR — Start-Up, Cont’d.

Water Treatment

Proper water treatment is a specialized industry 
IEC recommends consulting an expert in this field 
to analyze the water for compliance with the water 
quality parameters listed below, and to specify the 
appropriate water treatment regimen. The expert may 
recommend typical additives such as rust inhibitors, 
scaling preventative, antimicrobial growth agents, or algae 
preventatives. Anti-freeze solutions may also be used to 
lower the freezing point.

IEC water coil tubes and headers are constructed of 
copper. Multiple brass alloys may be present in the valve 
package, depending on unit configuration. It is the user’s 
responsibility to ensure the tube and piping materials 
furnished by IEC, are compatible with the treated water. 

Water Containing

Required Concentration

Sulphate

Less than 200 ppm

pH

7.0 – 8.5

Chlorides

Less than 200 ppm

Nitrate

Less than 100 ppm

Iron

Less than 4.5 mg/l

Ammonia

Less than 2.0 mg/l

Manganese

Less than 0.1 mg/l

Dissolved Solids

Less than 1000 mg/l

CaCO

3

 Hardness

300 - 500 ppm

CaCO

3

 Alkalinity

300 - 500 ppm

Particulate Quantity

Less than 10 ppm

Particulate Size

800 micron max

Water System Balancing

A complete knowledge of the hydronic system, along with 
its components and controls, is essential to proper water 
system balancing. This procedure should not be attempted 
by unqualified personnel. The system must be complete, 
and all components must be in operating condition 
BEFORE beginning water system balancing operations.

Each hydronic system has different operating 
characteristics depending on the devices and controls 
used in the system. The actual balancing technique may 
vary from one system to another.

After the proper system operation is established, the 
appropriate system operating conditions such as various 
water temperatures and flow rates should be recorded in 
a convenient place for future reference.

Before and during water system balancing, conditions may 
exist due to incorrect system pressures which may result 
in noticeable water noise or undesired valve operation. 
After the entire system is balanced, these conditions will 
not exist on properly designed systems.

Controls Operation

Before proper control operation can be verified, all other 
systems must be operating properly. The correct water 
and air temperatures must be present for the control 
function being tested. Some controls and features are 
designed to not operate under certain conditions. For 
example, on a two-pipe cooling/heating system with 
auxiliary electric heat, the electric heater cannot be 
energized with hot water in the system.

A wide range of controls, electrical options and 
accessories may be used with the equipment covered in 
this manual. Consult the approved unit submittals, order 
acknowledgements, and other literature for detailed 
information regarding each individual unit and its controls. 
Since controls and features may vary from one unit to 
another, care should be taken to identify the controls 
used on each unit and their proper control sequence. 
Information provided by component manufacturers 
regarding installation, operation, and maintenance of their 
individual controls is available upon request.

When changing from one mode to another (cooling to 
heating or heating to cooling), it may take some time to 
actually notice a change in the leaving air temperature. 
In addition, some units may be designed for a very low 
air temperature rise in heating. Before declaring a unit 
inoperative or a component defective, it may be necessary 
to verify operation by more than one method.

Содержание miniReStoramod

Страница 1: ...Build Your Reputation on Ours Modular Hi Rise Replacement Series MIY INSTALLATION OPERATION MAINTENANCE MANUAL miniReStoramod ...

Страница 2: ...ndependently In addition some systems may require repeated venting over a period of time to properly eliminate air from the system 15 Failure to provide proper water quality will void the fan coil unit s warranty 1 No attempt should be made to handle install or service any unit without following safe practices regarding mechanical equipment 2 WARNING Wear eye hand and limb protection at all times ...

Страница 3: ...Start Up 25 Recommended Spare Parts per 10 units 26 Terms and Conditions 2 Warnings and Cautions SECTION ONE Receipt Unpacking Inspection 4 Receipt 4 Unpacking and Inspection 5 Handling 6 Potential Unit Configurations 7 Special Arrangment Options SECTION TWO Product Line Specific Demolition Installation 10 Demolition Step by Step Guide 11 Installation 14 Riser to Unit Installation 14 Riser to Drai...

Страница 4: ... inert fluid or gas such as clear water or dry nitrogen to avoid possible damage or injury in the event of a leak or component failure during testing Always protect adjacent flammable material when welding or soldering Use a suitable heat shield material to contain sparks or drops of solder Have a fire extinguisher readily available The manufacturer assumes no responsibility for personal injury or...

Страница 5: ... that no force or pressure be applied to the coil or piping during handling Depending on the options and accessories some units could contain delicate components that may be damaged by improper handling Lifting or supporting the cabinet only at the top and bottom should be avoided to maintain the straight and square cabinet alignment The equipment covered in this manual IS NOT suitable for outdoor...

Страница 6: ...t Sup 90 90 HS D CR CS HR HS HR CR D CS H1 H1 HS HR CR D CS H1 Sup Ret Ret Sup 90 90 Sup Ret HS D CR CS HR S1 Sup Ret S1 S1 HS HR CR D CS Sup Ret HS HR CR D CS Ret Sup 90 90 HS D CR CS HR Single side and Top Supply Top Supply Only HS HR CR D CS C2 Sup Ret Supply Ret Sup HS HR CR D CS C2 Ret Sup Sup 90 90 C2 Sup HS D CR CS HR HS HR CR D CS HS HR CR D CS M2 Sup Ret Ret Sup Sup Supply M2 M2 Supply 90...

Страница 7: ...t Sup Ret Sup 90 HS D CR CS HR 90 HS HR CR D CS Q1 HS HR CR D CS Q1 Q1 90 HS D CR CS HR 90 Sup Ret Ret Sup Sup Ret HS HR CR D CS E2 HS HR CR D CS E2 E2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR 90 E2 Supply Supply Supply HS HR CR D CS F2 HS HR CR D CS F2 F2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR 90 Supply Supply Supply HS HR CR D CS J2 HS HR CR D CS J2 J2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR ...

Страница 8: ... Ret Sup K2 K2 90 90 Sup Ret HS D CR CS HR Sup Sup Sup HS HR CR D CS P2 HS HR CR D CS P2 P2 90 HS D CR CS HR 90 Sup Ret Ret Sup Sup Ret Sup Sup Sup Sup Ret HS HR CR D CS Q2 Sup Ret HS HR CR D CS Q2 Q2 90 90 Ret Sup HS D CR CS HR Sup Sup Sup Sup Ret HS HR CR D CS T2 Sup Ret HS HR CR D CS T2 T2 90 90 Ret Sup HS D CR CS HR Sup Sup Sup Double side and Top Supply HS HR CR D CS B3 HS HR CR D CS B3 B3 Su...

Страница 9: ...t IEC for pricing and availability 2 Any special suply return arrangement may affect sound and performance 3 Risers pictured are shown for reference purposes only and adhere to the IEC standard convention 4 MRY MIY equipment is designed to use existing risers so risers are typically not sold with these models 5 Riser supply return configurations and temperatures should be labeled prior to demoliti...

Страница 10: ...placement will be 81 5 x 15 5 on most original units although every application may vary 4 Carefully cut drywall at outer edges of unit along penciled outline removing drywall from the floor to the top of existing fan coil unit to expose the entire front face 5 Cut and remove the upper front steel cabinet panel flush with the sidewall of the existing unit 6 Cut copper supply and return pipes with ...

Страница 11: ...of the new unit appropriate height and side orientation 7 Thoroughly check the old unit chassis and drywall cuts for any irregularities or protrusions that would prevent the new unit from sliding in seating and properly leveled 8 Attach the louvered deco panel frame onto the new slip in replacement chassis Be sure to remove the lower shipping brace bar from the deco frame before it is installed 9 ...

Страница 12: ... that no leaks are present 18 Purge water coils of air after isolation valves are opened to allow flow All models come with a manual air vent at minimum 19 Seal any remaining chassis openings as well as possible to minimize air leakage that would adversely affect unit performance 20 Make all high voltage electrical connections followed by low voltage connections 21 Reconnect electrical service at ...

Страница 13: ...ansition Panel 25 Attach the louvered return air deco panel to the new chassis using both of the 5 16 hex cam locks 26 Installation complete Clean up work area Submittals and product literature detailing unit operation controls and connections should be thoroughly reviewed BEFORE beginning the connection and testing of risers and piping To assure optimal unit performance the supply connection s ar...

Страница 14: ...le Connection point to any factory furnished and installed components Coil Figure 9 Back up Wrench Ball Valve Wrench Swivel Connection Riser to Drain Installation Figure 10 Drain Pan Drain Clamp Clamp Riser Knockout Unit Insulation P Trap Unit Wall Riser Riser Stubout 1 After the applicable Supply Return and Drain pipe knockouts have been removed carefully position the unit so that the riser ball ...

Страница 15: ... When testing with air or some other gas it might be necessary to tighten stem packing nuts on some valves to maintain air pressure in the riser Pressure testing risers with water should be done with the unit service valves closed to prevent flushing debris into the unit valve packages All leaks should be repaired before proceeding with the unit installation 13 After system integrity has been esta...

Страница 16: ... paint product stores It should be noted that the more conscientiously this preparation is done the more effective it will be After this preparation is accomplished the factory finish should provide excellent adhesion for a variety of air dried top coats Enamel will give a more durable higher gloss finish while latex will not adhere as well and will give a dull softer finish Factory aerosol touch ...

Страница 17: ... up operations Air System Balancing All duct stubs grilles filters and return access panels must be properly installed to establish actual system operating conditions BEFORE beginning air balancing operations Each individual unit and the attached ductwork is a unique system with its own operating characteristics For this reason air balancing is normally done by balance specialists who are familiar...

Страница 18: ...lues will typically result in higher sound power values than what are published by the manufacturer 4 Pleasae contact the Factory for special CFM or external static pressure applications Unit Model of Coil Rows Unit Voltage Pot Board Settings VDC Values 0 ESP CFM Values 0 ESP High Medium Low High Medium Low MIY04 3 120V 1 60 6 37 5 29 3 65 386 303 203 MIY04 4 120V 1 60 6 28 5 21 3 63 380 301 202 M...

Страница 19: ... result in higher sound power values than what are published by the manufacturer 4 Please contact the Factory for special CFM or external static pressure applications Unit Model and Size Total of Coil Rows Unit Voltage V PH Hz Proportional Analog T stat Fan Speed Limits VDC Tested CFM values at 0 ESP Max Min High Low MIY04 3 120V 1 60 6 37 3 65 386 203 MIY04 4 120V 1 60 6 28 3 63 380 202 MIY04 5 1...

Страница 20: ...cing technique may vary from one system to another After the proper system operation is established the appropriate system operating conditions such as various water temperatures and flow rates should be recorded in a convenient place for future reference Before and during water system balancing conditions may exist due to incorrect system pressures which may result in noticeable water noise or un...

Страница 21: ...ield lubrication is required Figure 13 Motor Blower Slide Out A Disconnect Plugs B Internal Circuit Breaker Should the assembly require more extensive service it is designed to slide out of the unit and be removed from the unit if necessary by disconnecting plugs see A shown in Figure 13 Remember to turn off the power to the unit and lockout the internal circuit breaker of the unit see B also show...

Страница 22: ...components and wiring of the unit This may vary from unit to unit Consult the wiring diagram attached to the unit for the actual type and number of controls provided on each unit The wiring diagram is affixed to the acoustical RA block off panel inside the unit It is visible when the return air panel is removed The wiring and controls are accessible through the flip down control box door see Figur...

Страница 23: ... discarded when dirty The optional factory permanent filter may be cleaned in hot soapy water to remove any trapped dirt It should then be set aside on edge to dry Before replacing the filter in the unit it should be recharged with some type of entrapment film such as Film Cor Recharging Oil The filter should be sprayed on both sides or submerged in the film to assure complete coverage The filter ...

Страница 24: ...including any numbers On warranty replacements in addition to the information previously listed the unit shipping code which appears on the upper right hand corner of the serial plate is required Contact the factory for authorization to return any parts such as defective parts replaced in warranty All shipments returned to the factory must be marked with a Return Authorization Number which is prov...

Страница 25: ... diagram Incoming power service or services are connected Install and connect furnish only parts which have not been factory installed Unit Start Up General visual unit and system inspection Check for proper fan rotation Record electrical supply voltage Check all wiring for secure connections Close all unit isolation valves Flush water systems Fill systems with water refrigerant Vent water systems...

Страница 26: ... In the event of a breach of the Limited Express Warranty IEC will only be obligated at IEC s option to repair the failed part or unit or to furnish a new or rebuilt part or unit in exchange for the part or unit which has failed If after written notice to IEC s factory in Oklahoma City Oklahoma of each defect malfunction or other failure and a reasonable number of attempts by IEC to correct the de...

Страница 27: ...Modular Hi Rise Replacement Series MIY INSTALLATION OPERATION MAINTENANCE MANUAL 27 This page intentionally left blank ...

Страница 28: ...ies MIY INSTALLATION OPERATION MAINTENANCE MANUAL Contact your local IEC Sales Representative for further details and pricing applicable to this product Visit our website iec okc com to find your local IEC Sales Rep IEC Part Number I100 90023660 IOM 056 Revision 9 9 2020 2016 2020 International Environmental Corporation IEC ...

Отзывы: