Modular Hi-Rise Replacement Series – MIY

INSTALLATION, OPERATION, & MAINTENANCE MANUAL

15

SECTION THREE — Finishing Installation

that may damage internal components or wiring. 
The mounting technique is a matter of choice; 
however, the unit should always be anchored 
securely to prevent movement during construction 
and riser expansion, contraction, and accidental 
contact.

 

After anchoring the new unit, it is then ready for 
the various service connections to be made such 
as riser and electrical connections.

 4.  All 

mini

ReStora

mod

 units use reinforced braided 

stainless steel flexible hose kits for piping between 
existing risers and unit water coils as shown 
in Figure 8. The hose kit design has threaded 
connections on each end. The hose kits allow for 
riser fluctuations due to thermal expansion.

 5.  Use a wrench to tighten the swivel connections. 

Use a backup wrench to hold the riser ball valve 
stationary to prevent it from bending or twisting 
during installation as shown in Figure 9. Be careful 
to not over tighten swivel connections.

 6.  Locate the unit’s coil unions, bracketed at the top 

of the coil assembly.

 7.  The plastic flare caps on the end of the coil fitting 

should be removed and discarded.

 8.  Use a wrench to tighten the swivel connections. 

Be careful to not over tighten swivel connections.

 9.  Locate the rubber p-trap drain hose, factory 

installed to the drain pan connection in the bottom 
of the unit as shown in Figure 10. 

10.  Push the rubber drain hose over the riser drain 

stub-out. Be careful that you do not bend the 
drain stub-out.

11.  Adjust the hose clamp over the riser stub-out and 

rubber hose to hold in place as shown in Figure 10. 

12.  Test for leaks. Any and all leaks should be repaired 

before proceeding with installation. When testing 
with air or some other gas, it might be necessary 
to tighten stem packing nuts on some valves to 

maintain air pressure in the riser. Pressure testing 
risers with water should be done with the unit 
service valves closed to prevent flushing debris 
into the unit valve packages. All leaks should 
be repaired before proceeding with the unit 
installation.

13.  After system integrity has been established, the 

riser insulation must be pulled back into place over 
the joint and glued or sealed to prevent sweating 
and heat loss or gain. All of the risers including the 
riser stub-outs should be properly covered with 
insulation. Internally mounted chilled water piping 
and valves are located over the drain pan and 
need not be insulated.

It is the responsibility of the installer to make sure that an 
isolation valve is installed between each supply and return 
piping connection to the unit.

SECTION THREE – Finishing Installation

Grille/Ductwork Installation

All ductwork and/or supply and return grilles should be 
installed in accordance with the installation instructions 
and project specifications. If not included on the unit or 
furnished from the factory, supply and return grilles should 
be provided as recommended in the product catalog.

NOTE:  Refer to CAUTION and WARNING on page 2 

(inside front cover) of this catalog.

The safest method of freeze protection is to use glycol in 
the proper percent solution for the coldest expected air 
temperature.

Electrical Connections

The unit serial plate lists the unit electrical characteristics 
such as the required supply voltage, fan and heater 
amperage and required circuit ampacities. The unit wiring 
diagram shows all unit and field wiring. Since each project 
is different and each unit on a project may be different, 
the installer must be familiar with the wiring diagram and 
serial plate on the unit BEFORE beginning any wiring.
The unit electrical power supply and entry location 

Содержание miniReStoramod

Страница 1: ...Build Your Reputation on Ours Modular Hi Rise Replacement Series MIY INSTALLATION OPERATION MAINTENANCE MANUAL miniReStoramod ...

Страница 2: ...ndependently In addition some systems may require repeated venting over a period of time to properly eliminate air from the system 15 Failure to provide proper water quality will void the fan coil unit s warranty 1 No attempt should be made to handle install or service any unit without following safe practices regarding mechanical equipment 2 WARNING Wear eye hand and limb protection at all times ...

Страница 3: ...Start Up 25 Recommended Spare Parts per 10 units 26 Terms and Conditions 2 Warnings and Cautions SECTION ONE Receipt Unpacking Inspection 4 Receipt 4 Unpacking and Inspection 5 Handling 6 Potential Unit Configurations 7 Special Arrangment Options SECTION TWO Product Line Specific Demolition Installation 10 Demolition Step by Step Guide 11 Installation 14 Riser to Unit Installation 14 Riser to Drai...

Страница 4: ... inert fluid or gas such as clear water or dry nitrogen to avoid possible damage or injury in the event of a leak or component failure during testing Always protect adjacent flammable material when welding or soldering Use a suitable heat shield material to contain sparks or drops of solder Have a fire extinguisher readily available The manufacturer assumes no responsibility for personal injury or...

Страница 5: ... that no force or pressure be applied to the coil or piping during handling Depending on the options and accessories some units could contain delicate components that may be damaged by improper handling Lifting or supporting the cabinet only at the top and bottom should be avoided to maintain the straight and square cabinet alignment The equipment covered in this manual IS NOT suitable for outdoor...

Страница 6: ...t Sup 90 90 HS D CR CS HR HS HR CR D CS H1 H1 HS HR CR D CS H1 Sup Ret Ret Sup 90 90 Sup Ret HS D CR CS HR S1 Sup Ret S1 S1 HS HR CR D CS Sup Ret HS HR CR D CS Ret Sup 90 90 HS D CR CS HR Single side and Top Supply Top Supply Only HS HR CR D CS C2 Sup Ret Supply Ret Sup HS HR CR D CS C2 Ret Sup Sup 90 90 C2 Sup HS D CR CS HR HS HR CR D CS HS HR CR D CS M2 Sup Ret Ret Sup Sup Supply M2 M2 Supply 90...

Страница 7: ...t Sup Ret Sup 90 HS D CR CS HR 90 HS HR CR D CS Q1 HS HR CR D CS Q1 Q1 90 HS D CR CS HR 90 Sup Ret Ret Sup Sup Ret HS HR CR D CS E2 HS HR CR D CS E2 E2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR 90 E2 Supply Supply Supply HS HR CR D CS F2 HS HR CR D CS F2 F2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR 90 Supply Supply Supply HS HR CR D CS J2 HS HR CR D CS J2 J2 Ret Sup Ret Sup Ret Sup 90 HS D CR CS HR ...

Страница 8: ... Ret Sup K2 K2 90 90 Sup Ret HS D CR CS HR Sup Sup Sup HS HR CR D CS P2 HS HR CR D CS P2 P2 90 HS D CR CS HR 90 Sup Ret Ret Sup Sup Ret Sup Sup Sup Sup Ret HS HR CR D CS Q2 Sup Ret HS HR CR D CS Q2 Q2 90 90 Ret Sup HS D CR CS HR Sup Sup Sup Sup Ret HS HR CR D CS T2 Sup Ret HS HR CR D CS T2 T2 90 90 Ret Sup HS D CR CS HR Sup Sup Sup Double side and Top Supply HS HR CR D CS B3 HS HR CR D CS B3 B3 Su...

Страница 9: ...t IEC for pricing and availability 2 Any special suply return arrangement may affect sound and performance 3 Risers pictured are shown for reference purposes only and adhere to the IEC standard convention 4 MRY MIY equipment is designed to use existing risers so risers are typically not sold with these models 5 Riser supply return configurations and temperatures should be labeled prior to demoliti...

Страница 10: ...placement will be 81 5 x 15 5 on most original units although every application may vary 4 Carefully cut drywall at outer edges of unit along penciled outline removing drywall from the floor to the top of existing fan coil unit to expose the entire front face 5 Cut and remove the upper front steel cabinet panel flush with the sidewall of the existing unit 6 Cut copper supply and return pipes with ...

Страница 11: ...of the new unit appropriate height and side orientation 7 Thoroughly check the old unit chassis and drywall cuts for any irregularities or protrusions that would prevent the new unit from sliding in seating and properly leveled 8 Attach the louvered deco panel frame onto the new slip in replacement chassis Be sure to remove the lower shipping brace bar from the deco frame before it is installed 9 ...

Страница 12: ... that no leaks are present 18 Purge water coils of air after isolation valves are opened to allow flow All models come with a manual air vent at minimum 19 Seal any remaining chassis openings as well as possible to minimize air leakage that would adversely affect unit performance 20 Make all high voltage electrical connections followed by low voltage connections 21 Reconnect electrical service at ...

Страница 13: ...ansition Panel 25 Attach the louvered return air deco panel to the new chassis using both of the 5 16 hex cam locks 26 Installation complete Clean up work area Submittals and product literature detailing unit operation controls and connections should be thoroughly reviewed BEFORE beginning the connection and testing of risers and piping To assure optimal unit performance the supply connection s ar...

Страница 14: ...le Connection point to any factory furnished and installed components Coil Figure 9 Back up Wrench Ball Valve Wrench Swivel Connection Riser to Drain Installation Figure 10 Drain Pan Drain Clamp Clamp Riser Knockout Unit Insulation P Trap Unit Wall Riser Riser Stubout 1 After the applicable Supply Return and Drain pipe knockouts have been removed carefully position the unit so that the riser ball ...

Страница 15: ... When testing with air or some other gas it might be necessary to tighten stem packing nuts on some valves to maintain air pressure in the riser Pressure testing risers with water should be done with the unit service valves closed to prevent flushing debris into the unit valve packages All leaks should be repaired before proceeding with the unit installation 13 After system integrity has been esta...

Страница 16: ... paint product stores It should be noted that the more conscientiously this preparation is done the more effective it will be After this preparation is accomplished the factory finish should provide excellent adhesion for a variety of air dried top coats Enamel will give a more durable higher gloss finish while latex will not adhere as well and will give a dull softer finish Factory aerosol touch ...

Страница 17: ... up operations Air System Balancing All duct stubs grilles filters and return access panels must be properly installed to establish actual system operating conditions BEFORE beginning air balancing operations Each individual unit and the attached ductwork is a unique system with its own operating characteristics For this reason air balancing is normally done by balance specialists who are familiar...

Страница 18: ...lues will typically result in higher sound power values than what are published by the manufacturer 4 Pleasae contact the Factory for special CFM or external static pressure applications Unit Model of Coil Rows Unit Voltage Pot Board Settings VDC Values 0 ESP CFM Values 0 ESP High Medium Low High Medium Low MIY04 3 120V 1 60 6 37 5 29 3 65 386 303 203 MIY04 4 120V 1 60 6 28 5 21 3 63 380 301 202 M...

Страница 19: ... result in higher sound power values than what are published by the manufacturer 4 Please contact the Factory for special CFM or external static pressure applications Unit Model and Size Total of Coil Rows Unit Voltage V PH Hz Proportional Analog T stat Fan Speed Limits VDC Tested CFM values at 0 ESP Max Min High Low MIY04 3 120V 1 60 6 37 3 65 386 203 MIY04 4 120V 1 60 6 28 3 63 380 202 MIY04 5 1...

Страница 20: ...cing technique may vary from one system to another After the proper system operation is established the appropriate system operating conditions such as various water temperatures and flow rates should be recorded in a convenient place for future reference Before and during water system balancing conditions may exist due to incorrect system pressures which may result in noticeable water noise or un...

Страница 21: ...ield lubrication is required Figure 13 Motor Blower Slide Out A Disconnect Plugs B Internal Circuit Breaker Should the assembly require more extensive service it is designed to slide out of the unit and be removed from the unit if necessary by disconnecting plugs see A shown in Figure 13 Remember to turn off the power to the unit and lockout the internal circuit breaker of the unit see B also show...

Страница 22: ...components and wiring of the unit This may vary from unit to unit Consult the wiring diagram attached to the unit for the actual type and number of controls provided on each unit The wiring diagram is affixed to the acoustical RA block off panel inside the unit It is visible when the return air panel is removed The wiring and controls are accessible through the flip down control box door see Figur...

Страница 23: ... discarded when dirty The optional factory permanent filter may be cleaned in hot soapy water to remove any trapped dirt It should then be set aside on edge to dry Before replacing the filter in the unit it should be recharged with some type of entrapment film such as Film Cor Recharging Oil The filter should be sprayed on both sides or submerged in the film to assure complete coverage The filter ...

Страница 24: ...including any numbers On warranty replacements in addition to the information previously listed the unit shipping code which appears on the upper right hand corner of the serial plate is required Contact the factory for authorization to return any parts such as defective parts replaced in warranty All shipments returned to the factory must be marked with a Return Authorization Number which is prov...

Страница 25: ... diagram Incoming power service or services are connected Install and connect furnish only parts which have not been factory installed Unit Start Up General visual unit and system inspection Check for proper fan rotation Record electrical supply voltage Check all wiring for secure connections Close all unit isolation valves Flush water systems Fill systems with water refrigerant Vent water systems...

Страница 26: ... In the event of a breach of the Limited Express Warranty IEC will only be obligated at IEC s option to repair the failed part or unit or to furnish a new or rebuilt part or unit in exchange for the part or unit which has failed If after written notice to IEC s factory in Oklahoma City Oklahoma of each defect malfunction or other failure and a reasonable number of attempts by IEC to correct the de...

Страница 27: ...Modular Hi Rise Replacement Series MIY INSTALLATION OPERATION MAINTENANCE MANUAL 27 This page intentionally left blank ...

Страница 28: ...ies MIY INSTALLATION OPERATION MAINTENANCE MANUAL Contact your local IEC Sales Representative for further details and pricing applicable to this product Visit our website iec okc com to find your local IEC Sales Rep IEC Part Number I100 90023660 IOM 056 Revision 9 9 2020 2016 2020 International Environmental Corporation IEC ...

Отзывы: