ID Swing Gate 2400
4
2.1 Installation notes & suggestions
Note:
Disconnect all circuits during installation
►►
Installation Suggestion:
1)
Cables should run in ductworks at 60mm depth to end up between mounting frames.
2)
If the turnstiles installed outside, consider a higher depth for the ductworks.
3)
The installation should be done without any power connections to the gate.
4)
After the hole location is determined, drill the hole and embed the anchor bolt or expansion
bolt of M12. Concrete of at least 60mm thickness is recommended.
5)
If you install multiple devices please make sure to align them properly before drilling holes.
6)
Connect the power line and control line according to the wiring diagram and connect the
system protection ground wire.
7)
After successfully anchored and checked wiring turn on the power.
8)
After completion of the installation, check the connection condition of earth wire, connector
assembly for connecting line and all moving parts with the device. Make sure the connection is
firm in order to prevent failure caused by long time operation. If any screw or part is not
tightened, please tighten.
Figure 1)
Drawing of mounted anchor bolts
Figure 2)
Position of mounting frame/holes
2. Installation instructions