background image

Page 14

Mixed HW out

Mains CW in

Figure 1: Cold port of the blending valve connected to mains supply

NOT ALLOWED

Mixed HW out

Mains CW in

Figure 3: Cold port of the blending valve connected to mains supply

to the vessel after the inlet control group

Balanced cold feed

Mixed HW out

Mains CW in

Balanced cold feed

Non-Return Valve (must be fitted)

Figure 2: Cold port of the blending valve connected to balanced cold

supply - NON-RETURN VALVE MUST BE FITTED

Fitting Blending Valves To The Unvented 

Ideal Pro Appliances

When fitting a blending valve to the unvented 

appliances, it is important that the installation 

does not contravene the G3, WRC and Health 

and Safety directives or the manufacturers 

recommendations. If this is the case, then 

the warranty should be null & void. The key 

requirements to comply with these regulations 

are: -

1.  Any fitting or material in contact with 

potable water (e.g. a blending valve) must 

be approved by WRC or an equivalent body.

2.  Connections or wiring arrangements must 

not bypass any safety devices.

3.  Any expansion due to heating must not be 

allowed to expand back into the cold mains.

4.  The settings of any safety devices must not 

be tampered with or adjusted.

The diagrams opposite shows how the    

blending valve can be piped onsite. 

Figure 1 shows the cold water port of the 

blending valve connected to the mains cold 

water supply before the inlet control group. 

This arrangement is completely unacceptable 

and illegal because: -

•  the water is allowed to expand in to mains 

cold water supply.

•  the vessel will be charged to the incoming 

mains supply which may be considerably 

higher than the working pressure of the 

vessel.  

If this arrangement is used then the Ideal Boilers 

warranty will not be valid.

Figure 2 shows the cold water port of the 

blending valve connected to the balanced 

cold water outlet. This arrangement will only 

be acceptable if a WRAS approved non-return 

valve is fitted, otherwise: -

•  during the heating cycle, the water will 

expand back into the mains supply, as the 

regulating valve must not be relied upon 

to act as a check valve under all operating 

conditions.

•  depending upon the characteristics of the 

blending valve, hot water may also flow from 

the balanced cold water taps.

Figure 3 shows the cold port of the blending 

valve connected to the cold water supply to the 

vessel after the inlet control group.  This should 

be the preferred method. It is recommended 

that the installer should ensure that there is no 

gravity circulation in the pipework connected to 

the cold port. If necessary, this can be achieved 

by fitting a non-return valve or using a thermal 

trap.

INSTALLATION

INSTALLATION

Содержание PRO Series

Страница 1: ...safety and performance speci cation that we require Do not use reconditioned or copy parts that have not been clearly authorised by Ideal For the very latest copy of literature for speci cation and m...

Страница 2: ...heir safety Children should be supervised at all times to ensure they do not play with the appliance This information is provided to assist generally in the selection of equipment Responsibility for s...

Страница 3: ...ressure Primary heat exchanger Indirect models 6 bar Immersion heater rating 3kW 240V AC All cylinders are manufactured in accordance with the requirements of BS EN 12897 The tundish must be positione...

Страница 4: ...ro Indirect Ideal Pro Indirect is an unvented hot water storage cylinder and is provided with a high efficiency internal primary coil which is designed for use with a gas or oil boiler and is suitable...

Страница 5: ...Dual control overheat stat pocket 22mm 8 Primary return 22mm 9 Primary flow 22mm Part G3 loose components supplied in a separate box A Combination inlet group incorporating pressure reducing valve st...

Страница 6: ...Pressure Regulator 3 bar inlet group c w balance cold supply expansion vessel connection and expansion valve set at 4 5 bar Expansion Vessel size Pre charged to 3 bar Watts kW 24hr Litres kg kg bar L...

Страница 7: ...Peak Immersion Heater High Level Cold Feed 22mm Connection Off Peak Immersion Heater Low Level Volume of On Peak Water Heated Dual Control Overheat Stat 22mm Primary Return Connection 22mm Primary Fl...

Страница 8: ...es 1 shower room Bedsit 0 180 1 bathroom 2 2 180 1 bathroom 4 3 180 1 bathroom separate shower room 6 4 180 1 bathroom 2 separate shower rooms or 2 bathrooms 7 5 180 2 bathrooms separate shower room 7...

Страница 9: ...k is kept to a minimum Shower Fittings Aerated taps are recommended to prevent splashing Any type of shower mixing valve canbeusedaslongasboththehotandcoldsuppliesaremainsfed However allmains pressure...

Страница 10: ...he discharge be of metal and a Be at least one pipe size larger than the nominaloutletsizeofthesafetydeviceunless its total equivalent hydraulic resistance exceeds that of a straight pipe 9m long i e...

Страница 11: ...genuine replacement parts supplied or approved by Ideal Boilers are used All parts are available to approved installers from Ideal Boilers Tundish Hot Outlet To Drain PRV NRV Stop Tap Kitchen Cold Ta...

Страница 12: ...Danger of electrocution before making any adjustments to the thermostat isolate the immersion heater from the mains electricity supply at the fuse spur unit The immersion heater thermostats incorpora...

Страница 13: ...shed by means of a temporary connection between the circuit and a supply pipe provided a Listed double check valve or some other no less effective backflow prevention device is permanently connected a...

Страница 14: ...opposite shows how the blending valve can be piped onsite Figure 1 shows the cold water port of the blending valve connected to the mains cold water supply before the inlet control group This arrangem...

Страница 15: ...with stat Br B 4 core cable Outside Sensor Gr Ideal Logic Heat H with outside sensor For Logic System S ignore pump wiring IN L IN L N E SL2 SL1 Mains In Outside Sensor Ideal Logic Heat H with outside...

Страница 16: ...R Supplied with stat Br B 4 core cable Ideal Logic Heat H without outside sensor For Logic System S ignore pump wiring IN L IN L N E SL2 SL1 Mains In 1 9 8 7 6 5 4 3 2 10 11 12 N L 1 2 3 4 OFF ON OFF...

Страница 17: ...heat Stat Spade connectors required for earth connections Control Stat G Y Br R Supplied with stat Br B 4 core cable 1 9 8 7 6 5 4 3 2 10 11 12 N L 1 2 3 4 OFF ON OFF ON HW CH 1 2 3 4 Room Thermostat...

Страница 18: ...ed and refilled with the mains water immediately on completion of the disinfection procedure Damage caused through a failure to do this adequately will not be covered by the warranty Forthereasonsment...

Страница 19: ...ruction and blockage and are not passing any water 5 Check the condition and if necessary descale the heat exchangers in hard water areas 6 Check that water pressure downstream of pressure reducing va...

Страница 20: ...s electrical ensure that the immersion heaters are isolated from the mains before re setting the energy cut out If the immersion heater s need replacing this should be done with the units supplied fro...

Страница 21: ...tripped Check wiring links continuity and Re set END YES YES YES NO NO NO Switch on Set programmer Re set check wiring plumbing is correct Re set Is all wiring to the controls ok Replace thermostat Re...

Страница 22: ...Clear obstructions Is system free from restrictions blockages YES NO Is pressure reducing valve in combination valve working Clean or replace as required Is expansion vessel charge pressure correct R...

Страница 23: ...6748 3 Inlet group set at 3 bar c w expansion relief valve set at 4 5 bar 1 176750 4 12 litre expansion vessel 1 176751 5 18 litre expansion vessel 1 176752 6 24 litre expansion vessel 1 176753 7 35 l...

Страница 24: ...Page 24...

Страница 25: ...plumbed and pre wired for domestic hot water and one heating zone incorporating a sealed primary filling loop and mains cold feed inlet control components fitted The following pages only provide deta...

Страница 26: ...Drawing No Sheet No For Review Andrew T 14 09 2017 StainlessLite Pro PP Floor Template MIP 926 1 1 awing No MIP 926 P1 Rev No P1 Sh1 1 A3 Tolerance 3 0mm 1 4 1 2 3 4 5a 6 7 8 9 10 Cylinder Hot Outlet...

Страница 27: ...triction or valves fitted in the pipework between the boiler and the primary system safety valve 3 If the primary pipework from the boiler to the safety valve is more than 6 metres we recommend that t...

Страница 28: ...Heating 2 port valve 1 XG083 2 Hot water 2 port valve 1 XG083 3 Automatic primary heating byepass valve 1 XG019 4 Automatic air vent 1 FT434 5 28mm circulator gate valves 1 XB122 6 Filling loop compr...

Страница 29: ...rn Blue Or Gr Motor N OUT IN L Aux Sw HP22 2 PORT HTG VALVE Zone 1 8 N 6 7 Brn Blue Or Gr Motor N OUT IN L Aux Sw HP22 2 PORT DHW VALVE L N 13 N PUMP 15 14 N 11 10 9 PROGRAMMER N L ON ON LINKS WATER H...

Страница 30: ...Page 30...

Страница 31: ...tourbridge West Midlands DY8 1PA TELEPHONE 01384 442611 FAX 01384 442612 Water Savings Water Related Costs Can Be Reduced By Good Plumbing Practice TAPS MIXERS SHOWERS Unregulated 25 30 l m Regulated...

Страница 32: ...As more than one person is required for these products ensure that one person is taking the lead This may be you so ensure that each person that is helping is made aware of the weight and of the item...

Страница 33: ...of any obsolete product and will collect and deliver to any address in England Scotland and Wales excluding all islands Our normal working times excluding Bank Holidays are 8am 6pm Monday to Friday 8...

Страница 34: ...te will then be issued to the customer Heating and Hotwater Industry Council HHIC www centralheating co uk demonstrating compliance with the appropriate Building Regulations and then handed to the cus...

Страница 35: ...me Telephone No Comments Signature SERVICE 05 Date Engineer name Company name Telephone No Comments Signature SERVICE 07 Date Engineer name Company name Telephone No Comments Signature SERVICE 09 Date...

Страница 36: ...ning servicing of central heating systems Ideal Boilers Ltd PO Box 103 National Avenue Kingston Upon Hull HU5 4JN Tel 01482 492251 Fax 01482 448858 Registration No London 322 137 Ideal Technical Helpl...

Страница 37: ......

Страница 38: ......

Страница 39: ...surge in flow may be experienced which disappears as the pressure in the system stabilises This is quite normal with these types of systems and does not indicate a fault In some areas the water will i...

Страница 40: ...and performance speci cation that we require Do not use reconditioned or copy parts that have not been clearly authorised by Ideal For the very latest copy of literature for speci cation and maintenan...

Отзывы: