The boiler does not normally need a bypass but at least some 
radiators on the heating circuit, of load of at least 10% of the 
minimum boiler output, must be provided with twin lockshield 
valves so that this minimum heating load is always available. 

Note.

  Systems incorporating zone valves which could completely 

cut off the flow through the system must also include a bypass.

Balancing

1.  Set the programmer to ON.

1.18  WATER TREATMENT

1.17  SYSTEM BALANCING

Central Heating

The  Keston Combi

2

 range of boilers have an ALUMINIUM 

alloy heat exchanger.

 IMPORTANT 

  The application of any other treatment 

to this product may render the guarantee of Keston invalid.

The Keston System Filter will aid against the build up of iron 
oxide debris, however the below water treatment is also 
recommended by 

Keston

.

Keston

 

recommend Water Treatment in accordance with the 

Benchmark Guidance Notes on Water Treatment in Central 
Heating Systems.

If water treatment is used, 

Keston Heating 

recommend 

only the use of 

SCALEMASTER SM-1 PRO, FERNOX MBI, 

ADEY MC1, SENTINEL X100 or CALMAG CM100 

inhibitors and 

associated water treatment products, which must be used in 
accordance with the manufacturers’ instructions.

1.16  SYSTEM REQUIREMENTS - DHW

Domestic Hot Water

1.

  The DHW service must be in accordance with BS.5546 & 

BS6700.

2.

  Refer to Table 1 for minimum and maximum working 

pressures.  In areas of low mains water pressures the 
domestic hot water regulator may be removed from the 

DHW flow turbine cartridge.  The boiler will require the flow 

rate to be set to obtain a temperature rise of 35

o

C at the 

tap furthest from the boiler.

 

Refer to Section

3.20

3.

  The boilers are suitable for connection to most types of 

washing machine and dishwasher appliances.

4.

  If the shower/mixer valve does not incorporate non-return 

valves the following must be followed:

a.

  The cold inlet to the boiler is fitted with an approved  

 

  anti-vacuum or syphon non-return valve.

1.

  It is most important that the correct concentration of the 

water treatment products is maintained in accordance 
with the manufacturers’ instructions. 

2.

  If the boiler is installed in an existing system any 

unsuitable additives MUST be removed by thorough 

cleansing. BS7593:2019 details the steps necessary to 

clean a domestic heating system.

3.

  In hard water areas, treatment to prevent lime scale may 

be necessary -  however the use of artificially softened 

water is NOT permitted.

4.

  Under no circumstances should the boiler be fired before 

the system has been thoroughly flushed.

For further information contact:

Fernox 

 www.fernox.com  Tel: +44 (0) 3301 007750

Sentinel Performance Solutions

www.sentinelprotects.com  Tel: +44 (0) 1928 704330

Scalemaster Water Treatment Products

www.scalemaster.co.uk  Tel: +44 (0) 1785 811636

Calmag Ltd

.

www.calmag Ltd.com  Tel: +44 (0) 1535 210320

Adey

  www.adey.com  Tel: +44 (0) 1242 546700

 

b.

  Hot and cold water supplies to the shower are of

 

 

equal pressure.

5.  Hard Water Areas

 

Where the water hardness exceeds 200 mg/litre (200 ppm), 
it is recommended that a proprietary scale reducing device 

is fitted into the boiler cold supply within the requirements of 

the local water company.

 

IMPORTANT 

 Provision must be made to 

accommodate the expansion of DHW contained within the 

appliance. If the DHW inlet contains a back flow prevention 

device or non-return valve, e.g. a water meter, then a mini 

expansion vessel should be fitted between the device and 

the boiler in the cold inlet pipe.

Cold water, rising main and pipework in exposed areas 

need to be suitably lagged to prevent freezing.

Note  

DHW Expansion Vessel kit available from Keston.

2.  Close the manual or thermostatic valves on all radiators, 

leaving the twin lockshield valves (on the radiators 
referred to above) in the OPEN position.  

3.  Turn up the room thermostat and adjust the lockshield 

valve to give an uninterrupted flow through the radiator.

 

These valves should now be left as set.

4.  Open all manual or thermostatic radiator valves and 

adjust the lockshield valves on the remaining radiators, 
to give around 20

o

C temperature drop at each radiator.

5.  Adjust  the room thermostat and programmer to 

NORMAL settings.

CAUTION: 

Do not fill the heating system with softened 

water. Softened water could enhance corrosion.

Refer to Section

1.11

13

Installation and Servicing

 

Section 1 - General

Содержание Keston COMBI2 C30

Страница 1: ...that we require Do not use reconditioned or copy parts that have not been clearly authorised by Keston For the very latest copy of literature for specification and maintenance practices visit our webs...

Страница 2: ...no Equipped with a Supplementary Heater n a n a no no Combination Heater n a n a yes yes Nominal Heat Output for Space Heating Full Load P4 kW 24 3 24 3 Part Load P1 kW 8 8 Auxiliary Electricity Cons...

Страница 3: ...building size and its characteristics Collector Size in m2 Tank Volume in m3 Collector Efficiency in Tank rating A 0 95 A 0 91 B 0 86 C 0 83 D G 0 81 Solar Contribution from fiche of solar device Sea...

Страница 4: ...ES FOR THE INSTALLER WARNING Risk of injury or death CAUTION Risk of damage to objects Table of Acronyms CH Central Heating DHW Domestic Hot Water TRV Thermostatic Radiator Valve PRV Pressure Relief V...

Страница 5: ...eral Checks 36 2 36 Restart Procedure 37 2 37 Handing Over 37 Section 3 Servicing 38 3 1 Servicing Schedule 38 3 2 Removal Replacement of Components 39 3 3 Draining the Boiler 39 3 4 Boiler Front Pane...

Страница 6: ...Inlet Connection Cold Water 15 mm copper compression Outlet Connection Cold Hot Water 15 mm copper compression Flow Connection Central Heating 22 mm copper compression Return Connection Central Heatin...

Страница 7: ...ater outlet temp measure record Water flow rate at max setting measure record For condensing boilers only Condensate drain 23 24 For all boilers Complete sign hand over to customer For UK intallations...

Страница 8: ...variations and seasonal temperature fluctuations DHW flow rates temperature rise will vary requiring adjustment at the draw off tap At low DHW draw off rates the maximum temperature may exceed 65 C Th...

Страница 9: ...bt please enquire Unapproved control devices could invalidate the warranty of this appliance and infringe the Gas Safety Regulations 1 6 SAFE HANDLING OF SUBSTANCES No asbestos mercury or CFCs are inc...

Страница 10: ...g to allow use of different brands of pipework Refer to Section 2 16 Compartment Installations A boiler installed in a compartment does not require ventilation However a boiler installed in a compartm...

Страница 11: ...61 36 21 33 32 43 5 94 Refer to Section 2 18 278 700 100 Flue terminal 2 5 2 5 from case Underside View Water and Gas Connections CH Flow DHW Outlet Gas DHW Inlet CH Return CH Circuit Drain Data Plate...

Страница 12: ...necessary If the vessel s capacity is not sufficient an additional vessel must be installed on the return to the boiler If the system is not pressurised the cold water capacity must not exceed 143 li...

Страница 13: ...ce with the manufacturers instructions 2 If the boiler is installed in an existing system any unsuitable additives MUST be removed by thorough cleansing BS7593 2019 details the steps necessary to clea...

Страница 14: ...214 Venturi 215 Fan 217 Burner 218 Gasket Burner 219 Sump Clean Out Cover 223 Flue Manifold 224 Flue Manifold Top 227 Clamp Retaining Flue Turret 228 Hose Condensate Internal 229 Condensate Trap 231...

Страница 15: ...1x Valve CH G3 4 x 22 mm Filling Loop 15 1x Cap Female 16 1x Valve CH G3 4 x 22 mm 17 1x Pipe DHW Inlet 18 1x Nut G1 2 x 16 Brass Flat 19 1x Gas Cock 20 1x Coupling Accessory Bag Contents 21 9x Washe...

Страница 16: ...the flue and air holes preferably with 60mm core bore tool ensuring the holes are square to the wall 2 Drill 2 holes with a 7 5mm 8mm masonry drill and insert the plastic plugs provided for the wall...

Страница 17: ...ation Polypipe System 2000 muPVC Solvent Weld System 50mm Polypipe Code MU 301 4m length muPVC wastepipe 5 225 MU 313 50mm x 45 deg muPVC obtuse bend MU 314 50mm x 92 5 deg muPVC swept bend MU 310 50m...

Страница 18: ...surface Condensing boilers emit a visible plume of water vapour from the flue terminal this is normal It is the responsibility of the installer to judiciously select a terminal location that does not...

Страница 19: ...elbows 4 Straight lengths 2 2 3 5 4 0 15 15 65 Calculations 2 4 6 8 10 12 14 16 18 20 22 24 26 28 2 6 10 14 18 22 26 30 Acceptable Operating Area Keston Combi 35 Flue Air Pipe Length Flue Pipe Length...

Страница 20: ...e terminal is mounted 40 mm 40 mm 40 mm 40 mm P From a vertical structure on the roof NA NA 300 mm NA Q Above intersection with roof NA NA 150 mm NA 1 In addition for temperature and structural reason...

Страница 21: ...flue pack supplied with the boiler Remove boiler front panel Section 3 2 Remove air intake blanking plate by unscrewing 4 x M5 screws and put to one side leaving sponge gasket in place Fix air spigot...

Страница 22: ...ll Plate Flue Sleeve Flange 1 Cut hole in wall 2 Measure wall thickness 3 Cut sleeve length to match wall thickness remove burrs 4 Grout sleeve into wall with flange on external face 5 Slide flue pipe...

Страница 23: ...ions The use of an externally run condensate drainage pipe should only be considered after exhausting all internal termination options as described previously An external system must terminate at a su...

Страница 24: ...oof insulation 68 mm PVCU Strap on fitting Boiler with 75 mm sealed condensate trap Boiler with 75 mm sealed condensate trap Min 19 mm Internal pipe Min 30 mm Internal pipe Water Weather proof insulat...

Страница 25: ...ter installation and maintenance guide Failure to install the system filter correctly will affect boiler warranty WATER CONNECTIONS DHW 1 Fit the DHW inlet service valve blue handle and copper tail to...

Страница 26: ...ing loop Top Up 1 Connect the filling loop ensuring the washers are in place 2 Loosen the auto air vent dust cap Refer to Section 3 23 3 Turn the DHW Inlet handle blue to the horizontal position 4 Slo...

Страница 27: ...he control box into the service position unclip and swing back the installer wiring cover and latch into the retaining clips 4 Carefully pierce the grommet release the cable clamp via the screws and p...

Страница 28: ...e Room Stat on the RHS of the boiler installer connections labelled OpenTherm Frost Protection If parts of the pipework run outside the house or if the boiler will be left off for more than a day or s...

Страница 29: ...rter Valve 2 3 4 5 1 3 2 1 X7 1 2 3 4 5 6 7 8 X1 X2 X3 X4 X5 X6 X8 X9 1 2 3 1 2 3 4 5 6 1 2 3 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 1 2 3 4 5 5 4 3 2 1 X10 br b r bk r br bk b bk b r r b Chass...

Страница 30: ...hat this inlet pressure can be obtained with all other gas appliances in the property working Refer to Gas Supply page 10 2 25 COMMISSIONING AND TESTING Strain Relief If it is necessary to use an alte...

Страница 31: ...en the Outside Temperature Sensor is connected The graph only shows temperatures between 12 and 30 degrees for clarity Examples 1 If the CH Potentiometer Knob is set to display 22 C on the Boiler Disp...

Страница 32: ...ng effect from the boiler flue To fix the air sensor to the wall unscrew the sensor box plastic cover and screw plug the sensor body to the wall Wire a twin core 0 5 mm2 cable from the sensor to the b...

Страница 33: ...the radiator symbol DOMESTIC HOT WATER 12 With the boiler firing rotate the DHW Temp Knob A clockwise until a target of 65 C is shown and fully open a DHW tap The boiler should continue to run and the...

Страница 34: ...oom Thermostat or Timer Off Ready Press 2 31 PREHEAT FUNCTION Preheating will occur when the flow Temperature drops 15 C below the DHW target It will run until the flow temperature reaches 5 C below t...

Страница 35: ...maining 10 mins Exit Maximum DHW Rate Press The boiler will run at Maximum DHW Rate for 10mins as long as there is sufficient cooling load Target Fan Speed 1400rpm Actual Fan Speed 1400rpm Time remain...

Страница 36: ...temperature rise of approximately 35o C at the flow rate stated on page 8 under operation 3 Reduce the DHW draw off rate to about 3 l min 0 7 gpm and check that the boiler modulates to deliver DHW at...

Страница 37: ...consistent with the household requirements of both heating and hot water consumption 5 Explain the precautions necessary to prevent damage to the system and to the building in the event of the system...

Страница 38: ...eck is carried out if applicable and the water system is correctly refilled vented and re pressurised 2 Proceed to IMPORTANT IMPORTANT 1 If for any reason the condensate trap has been removed ensure t...

Страница 39: ...75 61 36 21 33 32 43 5 94 CH Flow DHW Outlet Gas DHW Inlet CH Return CH Circuit Drain 3 3 DRAINING THE BOILER DOMESTIC HOT WATER CIRCUIT 1 Close all the DHW water isolating valves on the boiler inlet...

Страница 40: ...2 bottom spring clips engage ensuring the 2 knobs and 4 buttons line up with the holes in the front panel 5 Re tighten the two retaining screws View from bottom of boiler View from top of boiler 1 2 3...

Страница 41: ...for blockage or damage 7 Clean the outside of the injector and use a small flue brush to clean the injector hole Do not use anything abrasive such as a file 8 Remove the screw and twist venturi anti c...

Страница 42: ...position 5 Carefully brush the ceramic burner with a soft non metallic bristle brush 1 1 Place thumb here Insert two fingers 1 SCAN for video 3 8 CLEANING THE HEAT EXCHANGER 1 Replace the sump cover p...

Страница 43: ...nsions shown If there is damage to the electrode continue to follow steps below for replacment 5 Unplug the ignition lead from the electrode 6 Remove the earth lead from the electrode 7 Remove the 2 s...

Страница 44: ...ti clockwise and pull forward to remove the cartridge Be prepared for some water release 3 Using a pair of pliers pull out the plastic filter flow regulator 4 Clean or replace filter as necessary Refe...

Страница 45: ...thermistor and reassemble Check the O ring is fitted thermistor is fully engaged and the clip correctly located Refer to Section 3 2 3 15 SPARK GENERATOR REPLACEMENT 1 Disconnect the leads from the sp...

Страница 46: ...connect gas and electrical connections 7 Refit the trap 8 Ensure all gas valve connections are gas tight with a gas soundness check up to the gas control valve Refer to Section 3 2 Refer to Section 3...

Страница 47: ...hows Installer Initialise spare PCB Yes Press Yes and the following screen is shown Select boiler type Option 1 of 2 Keston Press Next until Keston is shown Press Select Select Boiler Brand Option 1 o...

Страница 48: ...DHW FLOW TURBINE SENSOR REPLACEMENT 2 3 4 3 21 PRESSURE GAUGE REPLACEMENT 1 Drain the boiler 2 Remove the boiler front see section 3 2 lower the control panel and remove the control box cover 3 Ensur...

Страница 49: ...air vent head O ring seal is fitted 6 Check that the air vent cap is loose 7 Refill the boiler Check for leaks around the new air vent joint Refer to Section 3 31 Refer to Section 2 16 Refer to Secti...

Страница 50: ...s Refer to Section 3 2 Refer to Section 3 3 Refer to Section 3 18 Refer to Section 2 18 SCAN for video 1 Drain the boiler 2 Remove condensate trap 3 Remove the 2 hex screws securing the plate heat exc...

Страница 51: ...ate heat exchanger note orientation Refer to Section 3 25 9 Loosen the nut above pump and rotate the pipe 10 If required remove expansion vessel connection hose Refer to Section 3 31 11 If required re...

Страница 52: ...ection 2 18 3 Refer to Section 3 2 Refer to Section 3 3 Refer to Section 2 18 52 Installation and Servicing Section 3 Servicing SERVICING 3 28 PUMP HEAD REPLACEMENT 3 27 CH WATER PRESSURE SWITCH REPLA...

Страница 53: ...the thermistor 4 Fit the new thermistor check that the O ring is fitted and replace clip 3 29 FLOW THERMISTOR REPLACEMENT Refer to Section 3 2 Refer to Section 3 3 Refer to Section 2 18 5 Reassemble...

Страница 54: ...the condensate rubber pipe Refer to Section 3 18 No 2 14 Remove the two heat exchanger fixing screws 15 Remove the heat exchanger slide out of location bracket 16 If replacement sump required Rotate h...

Страница 55: ...the boiler CH circuit 6 Remove the retaining clip on the vessel water connection pipe and remove the pipe 7 Support the expansion vessel and unscrew the 2 screws from the securing bracket located on t...

Страница 56: ...3 60 o C 2 4 2 6 85 o C 1 0 1 1 Keston Technical Help Line 01482 443005 Spares 01482 498665 Exit Next Fault Help Only carry out the following tests if you are gas safe qualified Exit Next Fault Help...

Страница 57: ...from gas valve to PCB for continuity If the wiring is OK then replace the PCB NO Replace Spark Generator and harness as necessary NO Replace Electrode and associated harness as necessary NO Replace G...

Страница 58: ...wiring is OK then replace the PCB NO Replace Spark Generator and Harness as necessary NO YES Check electrode and associated harness for continuity visual condition and position Are these functioning...

Страница 59: ...Flow Thermistor Check the resistance using a suitable multimeter connected across the Thermistor s terminal pins Is the Thermistor value correct YES Is the wiring securely connected to the low voltag...

Страница 60: ...Sensor YES NO Securely connect the wiring at both the boiler and Outside Sensor NO 4 11 NO CH OPERATION BUT DHW WORKS OK Is Off shown underneath the rad on the display NO YES Press Mode button C unti...

Страница 61: ...turbine check for debris in turbine filter Replace turbine if necessary NO Adjust flow rates to achieve 35 C temp rise and check filter fitted in turbine is not blocked with debris NO Reconnect wirin...

Страница 62: ...nnection Check the resistance using a suitable multi meter connected across the thermistor s terminal pins Temperature Resistance k 25 o C 9 7 10 3 60 o C 2 4 2 6 Is the thermistor value correct YES N...

Страница 63: ...appliance Comprehensive spares parts information and details of approved Keston Parts Distributors are available on idealparts com Our Parts team are also available to help with your Keston Spare Part...

Страница 64: ...64 Installation and Servicing Section 6 Benchmark to Commissioning...

Страница 65: ...ually This must be carried out by a competent Gas Safe registered engineer The service details should be recorded on the Benchmark Service and Interim Boiler Work Record and left with the householder...

Страница 66: ...r or ft3 hr Central heating output left at factory settings Yes No If no what is the maximum central heating output selected kW Dynamic gas inlet pressure mbar Central heating flow temperature C Centr...

Страница 67: ...nufacturers instructions and BS 7593 It is only acceptable to not have undertaken this if the service engineers attendance visit was in between annual services to attend a non water facing component S...

Страница 68: ...ly check the integrity of the whole flue system to confirm that all components are correctly assembled fixed and supported Check that maximum flue lengths have not been exceeded and all guidance has b...

Страница 69: ...al are not obstructed Check that no seals e g Those on flue extensions have been displaced during installation Rectify if necessary Turn off appliance and call Ideal Technical Helpline for advice The...

Страница 70: ...ating Helpline 01482 443005 Ideal Heating Parts 01482 498665 keston co uk Ideal Boilers Ltd pursues a policy of continuing improvement in the design and performance of its products The right is theref...

Отзывы: