Auto Passport Installation Guide
Page 5
Copyright © Innovative Control Systems, Inc.
RFID Wiring Layout
The wiring layout is the same for one, two, three, or four lanes. There is one cable that houses five wires and they
connect from the RFID All-in-One Reader / Antenna back to its corresponding Auto Sentry
flex
. See Figure 6.
ICS SUPPLIED
35' CABLE
RFID WIRIG
ORIPLT LAT LAYNUO
AUON STORY FLTX
LANE #1
RFID READER / ANTENNA
LANE #3
RFID READER / ANTENNA
LANE #2
RFID READER / ANTENNA
THERE WILL BE THREE ALL-IN-ONE RFID
READER/ANTENNAS WITH 35' LEADS
THAT TERMINATE BACK TO THEIR OWN
AUTO SENTRY FLEX. THERE WILL BE (3)
35' CABLES PROVIDED.
RFID WIRIG PLA
TERMINATE THE CABLE FROM THE RFID ALL-IN-ONE RFID READER/
ANTENNA ENCLOSURE TO THE RIGHT-SIDE OF THE TERMINAL BLOCKS
INSIDE THE AUTO SENTRY FLEX HEAD AS FOLLOWS:
BLACK ALL I NT CABLT
ALL (5) WIRES ARE LABELED:
PNWTR WIRTS
ATTACH WIRE MARKED 24V(+) TO THE ORANGE TERMINAL BLOCK (24+)
ATTACH WIRE MARKED 24V(-) TO THE BLACK TERMINAL BLOCK (24-)
DAOA WIRTS
ATTACH WIRE MARKED TX TO THE ORANGE TERMINAL BLOCK (TX)
ATTACH WIRE MARKED RX TO THE YELLOW TERMINAL BLOCK (RX)
ATTACH WIRE MARKED GROUND TO THE WHITE TERMINAL BLOCK (GD)
Figure 6. Layout Triple Lane Example RFID Wiring Layout
AUON STORY LAT
CNDUIO DTOAIL
THIS DRAWING IS ONLY INTENDED TO SHOW THE CONDUIT
REQUIREMENTS FOR THE AUTO SENTRY ISLANDS IN DETAIL.
THIS DRAWING IS NOT TO SCALE.
LANE #1
AUTO
SENTRY
ISLAND
3/4"
CONDUIT
LANE #2
AUTO
SENTRY
ISLAND
1/2" CONDUIT STUBBED
OUT TO CONNECT WITH
GATE CLOSING LOOP
1/2" CONDUIT STUBBED OUT
TO CONNECT WITH GATE
CLOSING LOOP
1/2" CONDUIT STUBBED OUT TO
CONNECT WITH THE MERGE LOOP.
THE MERGE LOOP SHOULD BE RUN
TO THE TRAFFIC GATE IN LANE #1.
1" CONDUIT TO SITE
MAIN SERVICE
ELECTRICAL PANEL
NOTE:
ENSURE THAT ALL CONDUITS
RUNNING TO THE GATES ARE TIGHTLY
BUNDLED TOGETHER AS THE OPENING
IN THE BASE OF THE GATE IS ONLY 3- ¼
INCHES IN DIAMETER.
LOW VOLTAGE CONDUIT
HIGH VOLTAGE CONDUIT
3/4"
CONDUIT
RFID
TRUSS
BASE
1" CONDUITS
RFID
TRUSS
BASE
LANE #3
AUTO
SENTRY
ISLAND
3/4"
CONDUIT
1/2" CONDUIT STUBBED OUT
TO CONNECT WITH GATE
CLOSING LOOP
1" CONDUIT
1/2" CONDUIT
CONNECTING THE
TWO GATES
RFID
TRUSS
BASE
(9) - 1" CONDUITS:
•
THREE POWER CONDUITS GOING TO
THE POWER DISTRIBUTION BOX
WHICH POWERS THE AUTO SENTRY.
•
THREE POWER CONDUITS GOING
BACK TO THE MAIN SERVICE
ELECTRIC PANEL WHICH POWERS
THE HEAT EXCHANGERS.
•
THREE CONDUITS FOR LOW
VOLTAGE GOING TO THE LOW
VOTLAGE JUNCTION BOX.
½ CONDUIT STUB OUTS FOR
CONNECTION TO LOOPS
Figure 5. Triple Lane Example Conduit Layout
Conduit Detail (Triple Lane)