Start-up
26
iDRY iRDP CT 20-500
10 Start-up
10.1 Preliminary
stages
Note!
Exceeding of the operating parameters!
Ensure that the operating parameters comply with the nominal values indicated on the type plate of the
dryer (voltage, frequency, air pressure, air temperature, ambient temperature etc.).
Prior to delivery, this dryer was thoroughly tested, checked and packed. Please verify the reliability of the dryer during
the initial start-up and check the perfect functioning during the first operating hours.
The initial start-up must be carried out by qualified personnel.
During the installation and operation of this device, all national regulations regarding electronics and
any other federal and state ordinances, as well as local provisions, need to be adhered to.
The operator and the user must ensure that the dryer is not operated without panels.
10.2 Initial
start-up
Note!
The number of starts/stops by pressing the ON-OFF switch - pos. 1 control panel must be limited to six
per hour.
Irreparable damage can be caused by starting up the device too often.
The method below should be applied during the first start-up, after longer downtimes or subsequent to
maintenance works.
The start-up must be carried out by certified skilled personnel.
Processing sequence (see Section 8.1 "Control panel")
1. Ensure that all steps of the "Installation" chapter have been carried correctly.
2. Ensure that the connection to the compressed-air system is in accordance with the provisions and that the lines
are fixed and supported properly.
3. Ensure that the condensate drain pipe is fixed in accordance with the provisions and that it is connected with a
collection system or a container and open the drain service valve.
4. Ensure that the bypass system (if installed) is open and that the dryer is disconnected from the compressed-air
system.
5. Remove any packaging material and other items which may block the space around the dryer.
6. Establish the mains connection (plug into socket).
7. iRDP CT 200-500 3phase - switch on the main switch - pos. A control panel.
8.
NOTE!
iRDP CT 200-500 3phase - wait at least two hours before starting the dryer (the crankcase heater of the
compressor needs to heat up the compressor oil).
9. Start the dryer by switching on the ON-OFF switch on the control panel (pos. 1).
10. Make sure that the DMC 51 electronic control unit is switched on.
11. If the temperature displayed on the DMC51 electronic control unit is sufficiently high, verify that the refrigerating
compressor starts within a few minutes.
NOTE!
– With low temperatures, the refrigerating compressor will remain
OFF
12. Ensure that the fan runs properly
–
wait for the first interventions.
13. Wait until the dew point remains stable.
14. Slowly open the air inlet valve.
15. Slowly open the air outlet valve.
16. Slowly close the central bypass valve of the system (if installed).
17. Check the pipes for air leakage.
18. Ensure the proper functioning of the condensate drain cycle (wait for the first condensate discharges).
Note!
A dew point between 32°F (0°C) and +50°F (+10°C) displayed on the DMC 51 control unit is considered
to be correct according to the possible operating conditions (flow rate, air inlet temperature, ambient
temperature etc.).
Содержание iDRY iRDP CT 100
Страница 28: ...Technical data 28 iDRY iRDP CT 20 500 11 Technical data 11 1 Technical data iDRY iRDP CT 20 200 1 1 115 60...
Страница 29: ...Technical data iDRY iRDP CT 20 500 29 11 2 Technical data iDRY iRDP CT 20 500 2 1 230 60...
Страница 30: ...Technical data 30 iDRY iRDP CT 20 500 11 3 Technical data iDRY iRDP CT 200 500 3phase 4 3 460 60...
Страница 38: ...Maintenance troubleshooting spare parts and dismantling 38 iDRY iRDP CT 20 500...
Страница 39: ...Maintenance troubleshooting spare parts and dismantling iDRY iRDP CT 20 500 39...
Страница 42: ...Appendices 42 iDRY iRDP CT 20 500 13 1 2 Dryer dimensions iDRY iRDP CT 75...
Страница 43: ...Appendices iDRY iRDP CT 20 500 43 13 1 3 Dryer dimensions iDRY iRDP CT 100 150...
Страница 44: ...Appendices 44 iDRY iRDP CT 20 500 13 1 4 Dryer dimensions iDRY iRDP CT 200 250...
Страница 45: ...Appendices iDRY iRDP CT 20 500 45 13 1 5 Dryer dimensions iDRY iRDP CT 300 350...
Страница 46: ...Appendices 46 iDRY iRDP CT 20 500 13 1 6 Dryer dimensions iDRY iRDP CT 400 500...
Страница 47: ...Appendices iDRY iRDP CT 20 500 47 13 1 7 Dryer dimensions iDRY iRDP CT 200 250 3phase...
Страница 48: ...Appendices 48 iDRY iRDP CT 20 500 13 1 8 Dryer dimensions iDRY iRDP CT 300 350 3phase...
Страница 49: ...Appendices iDRY iRDP CT 20 500 49 13 1 9 Dryer dimensions iDRY iRDP CT 400 500 3phase...
Страница 51: ...Appendices iDRY iRDP CT 20 500 51 13 2 2 Exploded diagram iDRY iRDP CT 20 30...
Страница 52: ...Appendices 52 iDRY iRDP CT 20 500 13 2 3 Exploded diagram iDRY iRDP CT 50...
Страница 53: ...Appendices iDRY iRDP CT 20 500 53 13 2 4 Exploded diagram iDRY iRDP CT 75...
Страница 54: ...Appendices 54 iDRY iRDP CT 20 500 13 2 5 Exploded diagram iDRY iRDP CT 100...
Страница 55: ...Appendices iDRY iRDP CT 20 500 55 13 2 6 Exploded diagram iDRY iRDP CT 125 150...
Страница 56: ...Appendices 56 iDRY iRDP CT 20 500 13 2 7 Exploded diagram iDRY iRDP CT 200 250...
Страница 57: ...Appendices iDRY iRDP CT 20 500 57 13 2 8 Exploded diagram iDRY iRDP CT 300 350...
Страница 58: ...Appendices 58 iDRY iRDP CT 20 500 13 2 9 Exploded diagram iDRY iRDP CT 400 500...
Страница 59: ...Appendices iDRY iRDP CT 20 500 59 13 2 10 Exploded diagram iDRY iRDP CT 200 250 3phase...
Страница 60: ...Appendices 60 iDRY iRDP CT 20 500 13 2 11 Exploded diagram iDRY iRDP CT 300 350 3phase...
Страница 61: ...Appendices iDRY iRDP CT 20 500 61 13 2 12 Exploded diagram iDRY iRDP CT 400 500 3phase...
Страница 71: ...Appendices iDRY iRDP CT 20 500 71...
Страница 72: ...Independent Compressor Partners LLC Jeffersonville IN 47131 www icompressorpartners com 7425MUM289_EN_2014 09...