Chapter 6. Planning for installation site requirements
You must ensure that the location where you plan to install the IBM system meets
all requirements.
Plan your installation site with assistance from an IBM installation planning
representative (IPR) or an IBM service representative. Prepare the site in advance
so that professional movers or riggers can transport the equipment to the final site
within the computer room. If the site cannot be prepared before the delivery time,
you must make arrangements to have the professional movers return to finish the
transportation later. Only professional movers can transport the equipment.
An IBM service representative installs the XIV system. The IBM service
representative can only minimally reposition the rack within the room, as needed
to complete required service actions. Professional movers or riggers are required to
transport the XIV system rack as close to the installation site as possible because of
its weight. Professional movers or riggers are also required to relocate or dispose
of the XIV system.
Planning for floor and space requirements
You must ensure that the location of the XIV system meets space and floor
requirements.
Procedure
Complete the following steps to ensure that the planned installation location meets
space and floor load requirements:
1.
Decide whether the XIV system is to be installed on a raised floor.
2.
Determine whether the floor meets the floor-load requirements for the XIV
system.
3.
Calculate the amount of space need for the rack footprint and service clearance
requirements.
4.
Determine where to place the rack in the installation site, based on the
floor-load and space requirements.
5.
If the location has a raised floor, prepare the raised floor with cable cutouts and
required ventilation.
6.
If the location is not a raised floor, resolve any safety concerns that are caused
by the location of overhead-cable exits and cable routing.
7.
Provide your IBM service representative with the following information before
the installation:
a.
Whether under-floor or over-head power-cabling scheme is to be used.
b.
The distance of the rack from the power receptacles.
Raised or non-raised floor considerations
You can install the IBM XIV Storage System on a raised or a non-raised floor.
Raised floor considerations
Installing the racks on a raised floor provides the following benefits:
© Copyright IBM Corp. 2008, 2018
29
Содержание XIV Gen3 Series
Страница 1: ...IBM XIV Storage System Gen3 Models 281x 11x 281x 21x and 281x 314 Planning Guide SC27 5412 09 IBM...
Страница 6: ...vi IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 8: ...viii IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 10: ...x IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 16: ...xvi IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 24: ...xxiv IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 52: ...28 IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 87: ...AIX 7 Oracle Solaris 11 SPARC Solaris 11 INTEL HPUX HPUX 11i v3 IA64 Chapter 8 Management tool requirements 63...
Страница 88: ...64 IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 94: ...70 IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 116: ...92 IBM XIV Gen3 281x 11x 281x 21x and 281x 314 Planning Guide...
Страница 125: ......
Страница 126: ...IBM Printed in USA SC27 5412 09...