Installing the 2145 UPS-1U cable-retention bracket
The 2145 UPS-1U cable-retention bracket ensures that the power cable connection
between the 2145 UPS-1U and the SAN Volume Controller node is stable.
Install the bracket after you install the power and signal cable assembly that was
supplied with the node to connect the 2145 UPS-1U and the node.
You can attach the bracket by performing the following steps:
1.
Install the power cable into the rightmost power outlet on the rear of the 2145
UPS-1U.
2.
Remove the bracket and the two screws (shown in Figure 37) from the
packaging.
3.
Place the bracket over the power outlets on the right rear of the 2145 UPS-1U,
so that the two screw holes line up.
4.
Position the bracket with the power cable protruding through the rightmost slot
in the bracket.
5.
Secure the bracket in place with one screw on each side, as shown in Figure 38.
svc00201
Figure 37. 2145 UPS-1U power cable-retention bracket hardware
svc00200
Figure 38. 2145 UPS-1U power cable-retention bracket
42
IBM System Storage SAN Volume Controller: Models 2145-8F2 and 2145-8F4 Hardware Installation Guide
1
1
Содержание SAN Volume Controller 2145-8F2
Страница 2: ......
Страница 8: ...vi IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 24: ...xxii IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 54: ...30 IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 78: ...54 IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 80: ...56 IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 88: ...64 IBM System Storage SAN Volume Controller Models 2145 8F2 and 2145 8F4 Hardware Installation Guide...
Страница 95: ......
Страница 96: ...Printed in USA GC27 2221 00...