![HYTROL ProSort MRT Скачать руководство пользователя страница 4](http://html1.mh-extra.com/html/hytrol/prosort-mrt/prosort-mrt_installation-and-maintenance-manual_2194850004.webp)
• Conveyor Set-Up
1. mark a chalk line on floor to locate center of the conveyor (floor
mounted Conveyors).
2. Place the drive section in position.
3. Install remaining sections placing end without support on extend pivot
plate of previous section (figure 4A). Check “match mark” Numbers to see
that adjoining sections are in proper sequence
4. fasten sections
together with butt cou-
plings and pivot plates
(figure 4C). Hand
tighten bolts only.
5. Check to see that
conveyor is level
across width and length
of unit. Adjust supports
and ceiling hangers as
necessary.
6. Install electrical con-
trols and wire motor.
See page 7.
• Belt Installation
INSTALLING THE BELT
The conveyor drive belt is a green aramide continuous belt. To install belt
follow directions below
WARNING: Do not install belt with power on, remove air to
take-up .
NOTE: Belt will be wrapped around the discharge drive pulley
1. Unroll belt while inserting into the bottom cut out of bed spacer
and into the belt guide at top. Green conveying surface should be
showing at top. make sure belt is not twisted in the process.
2. Continue inserting belt from discharge to infeed. At infeed end
remove bolt attaching belt guard to infeed idler weldment , Loosen
bolt holding top flat belt idler to belt guard this will allow the guard
to pivot which will make room for the belt to be wrapped around
the top flat belt idler and snub over the bottom flat belt idler. Add
bolt to belt guard and tighten top flat belt idler bolt (figure 4d).
3. Next go to the pneumatic take-up near discharge end and
thread belt through take-up as shown in (figure 5A).
BELT TENSION
Note: for maximum efficiency, maintain just enough belt tension
so drive pulley will not slip when carrying the rated load. Over
tightening of belts will cause premature failure.
PNEUMATIC TAKE-UP:
The window guard can be removed to reveal the take-up idler position. The
pneumatic take-up can be adjusted by increasing the pressure at the filter
regulator (see fig. 5A). Then operating pressure will be determined by the
total length and unit load. Start with the pressure set at 20 psi. Increase by 2
psi until the drive pulley does not slip when carrying the rated load up to 30
psi. Replace all guards before operating.
INSTALLATION
• Support Installation
1. determine primary direction of product
flow. figure 4A indicates the preferred flow
as related to the drive.
2. Refer to “match-mark” numbers on ends
of conveyor sections. (figure 4A) Position
them in this sequence near the area of
installation.
3. Attach supports to both ends of drive
section and to one end of intermediate
or tail sections (figure 4A). Hand tighten
bolts only at this time. Conveyors angle
of incline will determine where the knee
brace mounting brackets are to be placed
when required.
4. Adjust elevation to required height.
ADJUST TO DESIRED ELEVATION
(AJUSTE A LA ALTURA DESEADA)
NOTE: ALLOW FOR BELT THICKNESS WHEN ADJUSTING SUPPORTS
(NOTA: DEJE ESPACIO SUFICIENTE PARA EL ESPESOR DE LA BANDA CUANDO AJUSTE LOS SOPORTES)
DRIVE SECTION
(SECCION DE DESVIACION)
INTERMEDIATE SECTION
(SECCION INTERMEDIA)
TRANSFER SECTION
(SECCION DE
TRANSFERENCIA)
TRANSFER SECTION
(SECCION DE TRANSFERENCIA)
PNEUMATIC TAKE-UP
(TENSIONADOR
NEUMATICO)
TAIL SECTION
(SECCION DE RETORNO)
“MATCH-MARK” NUMBERS
(ETIQUETAS DE SECUENCIA DE ARMADO)
FLOW
(FLUJO)
MARK
CONVEYOR F.O. #
ITEM TO
HYTROL CONVEYOR CO. INC.
JONESBORO, AR
P-1
1
2
34268
MARK
CONVEYOR F.O. #
ITEM TO
HYTROL CONVEYOR CO. INC.
JONESBORO, AR
P-1
2
1
34268
• Ceiling Hanger Installation
If conveyors are to be used in an overhead application, ceiling hangers may have
been supplied in place of floor supports.
figure 4B shows how a ceiling hanger mounts to a conveyor section. Ceiling
hangers should be mounted at section joints. for safety information concerning
conveyors mounted overhead, refer to “Installation Safety Precautions” on Pg 3.
SUPPORT PIPE
(TUBO DE SOPORTE)
JAM NUT
(CONTRA TUERCA)
SPACER
(ESPACIADOR)
CEILING HANGER ROD
(VARILLA COLGADA
AL TECHO)
JAM NUT
(CONTRA TUERCA)
PIPE RETAINER
(ABRAZADERA)
LOCK BOLT
(TORNILLO CANDADO)
SIDE CHANNEL
(CANAL LATERAL)
MOUNTING BOLTS
(TORNILLOS DE MONTAJE)
FIGURE 4B
NOTE: When installing ceiling hanger rods in an existing building, all
methods of attachment must comply with local building codes.
CONVEYOR SIDE CHANNEL
PIVOT PLATE
STATIONARY SUPPORT
BUTT COUPLING
(ACOPLES DE EXTREMO)
(PLACA PIVOTE)
(SOPORTE ESTACIONARIO)
(CANAL LATERAL DEL TRANSPORTADOR)
FIGURE 4C
FIGURE 4A
TOP FLAT
BELT IDLER
BELT
GREEN
SURFACE
BELT GUIDE
BELT GUARD
INFEED IDLER WELDMENT
BED SPACER
BOTTOM CUT OUT
BOTTOM FLAT
BELT IDLER
(GUIADE BANDA)
(SUPERFICIE
VERDE)
(BANDA)
(GUARDIA DE BANDA)
(TOP TENSOR DE LA
CORREA PLANA)
(SOLDADURA RODILLO DE ALIMENTACIÓN)
(TENSOR DE LA
CORREA PLANA
INFERIOR)
(INFERIOR ESPACIADOR
DE CAMA CORTADA)
FIGURE 4D
4
Содержание ProSort MRT
Страница 23: ...23...