KN INSTALLATION INSTRUCTIONS FOR VENT AND AIR PIPING
Vent and air piped through a side wall
(concentric termination)
6
Figure 19
Vertical venting/sidewall air
Table 6
Vent and air system components
Read before proceeding
The vent piping operates with positive pressure
. Th e vent
piping must be completely sealed and securely supported.
Use only the vent components listed in this manual
. Use
of any other materials could result in vent system failure.
Exposed vent pipe poses a potential burn hazard to people and
pets. Insulate or shield the pipe where necessary to prevent risk.
Never drill through, or install screws into
, the vent pipe or
vent components.
Seal test hole with high temperature silicone aft er each
combustion test and annual inspection to prevent gases and
condensation from leaking during appliance operation.
Failure to properly install the vent piping could result in fl ue
gas leakage, causing possible severe personal injury, death or
substantial property damage.
Code compliance
— Follow all applicable local codes when
installing the vent system. Where codes diff er from this
manual, follow code requirements. Contact Hydrotherm if you
have any questions regarding the installation.
Terminate the vent and air piping following the guidelines
in this manual. Avoid vent termination locations likely to be
aff ected by winds, snowdrift s, people and pets. Protect building
materials and vegetation from degradation caused by the fl ue
gases and condensation.
Vent piping
(see Figure 19)
1 — Boiler vent connection
❑
Th e vent connection at the boiler is for Heat-Fab EZ-Seal vent piping only.
EZ-Seal vent att achment
Insert EZ-Seal pipe male end into the boiler connection
(Do not cover
combustion test port)
. Make sure the locking tabs slide under the EZ-Seal
locking ring. Bend back locking tabs to complete the joint. Follow EZ-Seal
instructions to complete the vent piping installation.
Th e concentric vent/air termination must be done only with Saf-T Vent type SC
vent components. Th is requires that all of the vent piping be Saf-T Vent EZ-Seal for
compatibility. DO NOT apply this vent/air termination option using any other
vent materials.
KN-2
KN-4
Vent components
Heat-Fab
Heat-Fab
Vent piping/components
(incl. supports, thimbles, etc.)
EZ-Seal, 3-inch piping
Saf-T Vent SC fi ttings for
termination assembly
EZ-Seal, 4-inch piping
Saf-T Vent SC fi ttings for
termination assembly
Termination assembly:
• Single-wall adapter
• Air intake tee
• 6-inch straight section
• 12-inch straight section
• Wall plate (2 required)
• Termination adapter
• Mitered termination
SC03ADEZ
SC03TAD3
SC0366
SC03L12
SC03FS
SC03HT
9390
SC04ADEZ
SC04TAD3
SC0466
SC04L12
SC04FS
SC04HT
9490
Joint sealant, required
GE RTV106 or equivalent
Air components
Heat-Fab
Heat-Fab
Air piping/components
(also supports, thimbles, etc.)
3-inch PVC, CPVC, ABS,
galvanized or aluminum
4-inch PVC, CPVC, ABS,
galvanized or aluminum