Page 48
12.
Commissioning
Note:
The LPS nozzle system may only be operated by qualified
personnel.
Turning the LPS nozzle system off
Note:
Before the LPS nozzle system is put into operation, it
must be clear how to switch the system off.
»
Switch off Nozzle system using control switch (Pos.0).
»
Shut off water supply shut-off valve.
Check all cable connections
»
Check all cable connections for tightness.
Activating the LPS nozzle system
»
Operate main switch.
»
Set manometer to „open“
»
Open up water shut-off valve
»
Switch on unit using control switch (Pos.I).
»
Set commissioning control to permanent demand
steam production.
The following functions begin:
A self-test.
When humidity is demanded, the pump vane is operated and
directs the water at a pressure of up to 16 bar to the nozzle.
The water is atomized at the nozzle. All nozzles should not drip
and show an even spray pattern.
Further tests:
All electrically-powered functions must function.
»
Observe LPS nozzle system and let it run for 15-30
minutes. The air conditioning duct fan should be in ope-
ration so that the moisture produced can be blown
away. Should any leakages be evident then turn the
LPS nozzle system off.
»
Eliminate the leaks:
Attention, voltage!
Please observe all safety instructions while
working on live components.
Содержание LPS
Страница 1: ...LPS Humidifies and Cools ÁLPS Ä4 3Ö ENhÈ LPS 20130619 EN Operating manual ...
Страница 37: ...Page 37 8 Dimensions Pump Station View from below Side view Rear view ...
Страница 62: ...Page 62 14 2 3 1 Menu structure and parameter setting 4 3 ...
Страница 63: ...Page 63 15 EC declaration of conformity ...
Страница 69: ...Page 69 4 3 ...