MERCHANDISERS SHIPPED
WITH END INSTALLED
If the case was shipped with the end installed, two
long bolts were used to hold the shipping brace to
the end. If the shipping bolts are reinserted after
removing the brace, they will extend into the
product area. T
HEREFORE
,
BE SURE TO REPLACE
THESE BOLTS WITH THE SHORTER BOLTS PROVIDED
.
NOTE:
Be careful not to damage the factory installed
end while moving the case. Make sure that
tools are positioned past the end and beneath
the merchandiser’s support bar.
SHIPPING BRACES
Move the merchandiser as close
as possible to its permanent
location and then remove all
packaging. Check for damage
before discarding packaging.
Remove all separately packed
accessories such as kits and
shelves.
LEVELING
Merchandisers must be installed level to ensure
proper operation of the refrigeration system and to
ensure proper drainage of defrost water.
Ice may
build up from defrost water not draining out of
merchandiser if merchandiser is not leveled.
When leveling merchandisers, use a carpenter’s
level as shown. Leveling shims are provided with
each merchandiser for use if needed. The shims
are big enough so that you can level adjoining
merchandisers at the same time using one shim.
NOTES:
• B
EGIN LINEUP LEVELING FROM THE HIGHEST POINT OF
THE STORE FLOOR
.
• If shimming two corners, check to see if a shim is
needed in the center of the merchandiser. If a gap
exists between the support rail of the merchandiser
and the floor, a shim should be placed in the center.
Do NOT remove shipping braces until the
merchandisers are positioned
for installation.
WARNING
!
Levels
Front of Merchandiser
Serial Plate
Shim
NOTE:
Do not place levels
on Display Pans or
on Shelves.